EPA Clean Air Act 40 CFR Part 70

EPA Clean Air Act Title V Major Source Operating Permit Auditor

Audit industrial facility air emissions under Clean Air Act Title V (40 CFR Part 70/71), calculating 100 tpy criteria pollutant limits, nonattainment area major source thresholds, 10/25 tpy HAP limits, and synthetic minor operational safe harbors.

Air Emissions & Location Parameters

Thresholds drop drastically in Severe and Extreme nonattainment zones.
Major source threshold: 10 tpy.
Major source threshold: 25 tpy.
Synthetic minor limits can legally cap PTE below major source thresholds.

Title V Permitting Determination Minor Source

Title V Major Source Classification: MINOR SOURCE / AREA SOURCE
Governing Ozone Major Threshold: 100 Tons / Year
HAP Threshold Compliance: Below 10/25 tpy Limits
Title V Operating Permit Required? NOT REQUIRED
Mandatory Reporting Burden: Standard Minor Source Reports
Clean Air Act Statutory Analysis: Evaluating facility potential to emit against 40 CFR Part 70.

Environmental Compliance Actions:

  • Maintain rolling 12-month records of fuel usage and VOC/HAP solvent purchases.
  • Verify emissions remain below major source thresholds at all operating hours.
  • Submit annual minor source emissions inventory to state air agency.

Comprehensive Guide to Clean Air Act Title V Operating Permits

Title V of the 1990 Clean Air Act Amendments (codified at 42 U.S.C. § 7661 et seq. and implemented through 40 CFR Parts 70 and 71) established a centralized, federally enforceable operating permit program. Title V does not typically impose new substantive emission limits, but consolidates all applicable federal, state, and local air regulations—including NSPS, NESHAP/MACT, and SIP rules—into a single comprehensive legal document.

1. Major Source Thresholds and Nonattainment Reductions

The determination of whether a facility requires a Title V permit hinges on its Potential to Emit (PTE), defined as the maximum capacity of a stationary source to emit any air pollutant under its physical and operational design:

2. The Synthetic Minor Safe Harbor

Facilities whose uncontrolled equipment capacity exceeds 100 tpy can legally avoid Title V permitting by becoming a Synthetic Minor Source. The facility enters into a state-issued construction permit or operating agreement that contains practically enforceable limits—such as capping annual operating hours, limiting fuel throughput, or requiring continuous operation of an incinerator or baghouse—holding actual emissions safely below major source cutoffs.

3. Responsible Official Personal Liability (40 CFR § 70.5(d))

Title V permits impose unprecedented personal legal exposure on corporate managers. Every annual compliance certification must be signed by a "Responsible Official" who certifies under penalty of law that, based on reasonable inquiry, the statements are true, accurate, and complete. Criminal penalties under CAA § 113(c) include fines up to $250,000 and imprisonment up to 5 years for knowing false statements.

Frequently Asked Questions Regarding Title V Permits

What emission levels trigger a Clean Air Act Title V major source permit? +
Under 40 CFR Part 70, a facility is classified as a Title V 'Major Source' if its potential to emit (PTE) meets or exceeds: (1) 100 tons per year (tpy) of any criteria air pollutant (NOx, VOC, SO2, CO, PM10, PM2.5, Lead); (2) 10 tpy of any individual Hazardous Air Pollutant (HAP); or (3) 25 tpy of any combination of HAPs.
How do nonattainment areas affect Title V major source thresholds? +
In ozone nonattainment areas, the major source threshold for VOC and NOx drops significantly: 50 tpy in Serious areas, 25 tpy in Severe areas, and 10 tpy in Extreme nonattainment areas. Similar reductions apply in Serious PM10 and PM2.5 nonattainment areas (70 tpy).
What is a 'Synthetic Minor' source under Title V? +
A synthetic minor source is a facility whose uncontrolled potential to emit (PTE) exceeds major source thresholds, but which accepts federally enforceable operational limitations (such as operating hour caps, throughput limits, or mandatory pollution control device efficiency) in a minor source permit to keep actual emissions below major source levels, avoiding Title V permitting.
What certifications are required by a Responsible Official under Title V? +
Under 40 CFR § 70.5(d) and § 70.6(c)(5), any application, report, or compliance certification submitted under Title V must contain a certification of truth, accuracy, and completeness signed by a 'Responsible Official' (typically a corporate officer or plant manager). False statements carry federal criminal penalties under Section 113(c) of the Clean Air Act.