EPA Clean Air Act Title V Major Source Operating Permit Auditor

Statutory compliance auditor under Clean Air Act Title V (42 U.S.C. §§ 7661-7661f) and 40 CFR Part 70/71. Audit Potential to Emit (PTE) thresholds for criteria pollutants (100 tpy) and Hazardous Air Pollutants (10/25 tpy HAP), synthetic minor caps, and CAA § 113 penalties.

1. Facility Emissions & Area Designation
2. Enforceable Limits & Permitting Status
Regulatory Classification & Penalties
TITLE V MAJOR SOURCE PERMIT REQUIRED
Statutory Major Source Classification
Criteria PTE (120 tpy) >= 100 tpy Threshold
Subject to 40 CFR Part 70 mandatory operating permit program
HAP Major Source Status (CAA § 112)
Area Source for HAPs (8 tpy single / 22 tpy agg)
Under 10 tpy single / 25 tpy aggregate thresholds
Clean Air Act Section 113 Civil Penalty Exposure
$0.00
Statutory inflation-adjusted max: $117,468 per day of unpermitted operation
Regulatory Assessment: Potential to emit exceeds 100 tpy threshold. Title V operating permit application required within 12 months of commencing operation under 40 CFR § 70.5(a)(1).

Frequently Asked Questions (Clean Air Act Title V)

What constitutes a 'Major Source' requiring a Title V operating permit under the Clean Air Act?
Under Clean Air Act Title V (42 U.S.C. § 7661(2)) and EPA regulations at 40 CFR § 70.2, a stationary facility is classified as a 'Major Source' and must obtain a Title V operating permit if its Potential to Emit (PTE)—operating at maximum capacity 8,760 hours per year without federally enforceable limits—equals or exceeds: (1) 100 tons per year (tpy) of any criteria air pollutant (PM10, PM2.5, SO2, NOx, CO, VOC, or Lead) in attainment areas (or as low as 10 to 50 tpy in severe or extreme ozone nonattainment areas); (2) 10 tons per year of any single Hazardous Air Pollutant (HAP) listed under CAA Section 112(b); OR (3) 25 tons per year of any combination of HAPs.
What is 'Potential to Emit' (PTE) and how can a facility establish 'Synthetic Minor' status?
Potential to Emit (PTE) is defined under 40 CFR § 70.2 as the maximum capacity of a stationary source to emit any air pollutant under its physical and operational design. Any physical or operational limitation on capacity—including air pollution control equipment, restrictions on operating hours, or limitations on the type or amount of material combusted, stored, or processed—is treated as part of its design ONLY if the limitation is federally enforceable. A facility whose uncontrolled capacity exceeds major source thresholds can obtain a 'Synthetic Minor' permit by accepting legally and practically enforceable limits that keep emissions below the 100 tpy and 10/25 tpy triggers, thereby avoiding Title V permitting.
What are the mandatory compliance reporting obligations for Title V permittees?
Title V permit holders must comply with rigorous ongoing monitoring and reporting under 40 CFR § 70.6: (1) Semi-Annual Monitoring Reports: submittal of all required monitoring records at least every 6 months, identifying all deviations; (2) Prompt Deviation Reporting: reporting of permit deviations causing excess emissions within 24 to 48 hours or as specified in the permit; and (3) Annual Compliance Certification: a comprehensive written statement certified under penalty of perjury by a 'Responsible Official' confirming continuous or intermittent compliance with each individual permit term and condition.
What civil penalties apply to operating a major source without a Title V permit?
Under Clean Air Act Section 113(b) (42 U.S.C. § 7413(b)) as adjusted under the Federal Civil Penalties Inflation Adjustment Act, operating a major source without a required Title V permit or violating permit conditions carries federal civil judicial penalties of up to $117,468 per day per violation. Furthermore, knowing violations carry criminal felony penalties of up to 5 years imprisonment and corporate fines for responsible corporate officers.