Federal Environmental Law · 33 U.S.C. § 1344

CWA Section 404 Wetlands Permit Auditor

Evaluate U.S. Army Corps of Engineers (USACE) dredge & fill permits: post-Sackett WOTUS continuous surface tests, Nationwide Permit (NWP) thresholds, LEDPA sequencing, and mitigation ratios.

Aquatic Resource & Impact Parameters

Direct physical fill or excavation in waters. > 0.5 acre triggers Individual Permit.
Off-site and on-site upland alternatives evaluated and rejected as impracticable (LEDPA).
State Section 401 Water Quality Certification (WQC) obtained or waived.
Compensatory mitigation credits reserved at approved USACE wetland mitigation bank.

Permit Determination & Mitigation Ratios

NATIONWIDE PERMIT (NWP) WITH PCN ELIGIBLE
Jurisdictional Status
Federal WOTUS
Permit Pathway
Nationwide Permit (NWP)
Compensatory Mitigation
0.70 Acres (2:1 Ratio)

Clean Water Act Section 404 Precedents & Guidelines

What is the WOTUS jurisdictional test after Sackett v. EPA (2023)?
In Sackett v. EPA, 598 U.S. 651 (2023), the U.S. Supreme Court narrowed the definition of Waters of the United States (WOTUS). Under the ruling, CWA Section 404 jurisdiction over adjacent wetlands requires a two-part test: (1) the adjacent body of water must be a relatively permanent water connected to traditional interstate navigable waters; and (2) the wetland must have a continuous surface connection to that body, making it difficult to determine where the water ends and the wetland begins. Isolated wetlands are no longer federally jurisdictional under Section 404.
What is the difference between a Nationwide Permit (NWP) and an Individual Permit?
Nationwide Permits (NWPs) are general permits issued by the U.S. Army Corps of Engineers (USACE) for activities with minimal adverse environmental effects (generally up to 0.5 acre of wetland impact). Individual Permits are required for larger, more complex impacts (> 0.5 acre), requiring extensive public notice, NEPA environmental reviews, and state Section 401 Water Quality Certification.
What is the LEDPA standard under EPA Section 404(b)(1) Guidelines?
Under 40 CFR Part 230, no discharge of dredged or fill material may be permitted if there is a Least Environmentally Damaging Practicable Alternative (LEDPA) to the proposed discharge which would have less adverse impact on the aquatic ecosystem. For non-water-dependent activities, practicable alternatives not involving wetlands are rebuttably presumed to exist.
What is Pre-Construction Notification (PCN)?
Pre-Construction Notification (PCN) is a formal notification submitted to the USACE district engineer prior to commencing work under a Nationwide Permit. It is typically required if the activity will result in the loss of greater than 0.10 acre of waters of the U.S., or if designated critical habitats or historic properties are present.
What are the compensatory wetland mitigation ratios?
Under the federal Compensatory Mitigation Rule (33 CFR Part 332), unavoidable impacts to wetlands must be offset through compensatory mitigation. Ratios typically range from 1.5:1 to 3:1 (acres of mitigation provided per acre of wetland lost), depending on the wetland quality, type, and whether mitigation is performed via mitigation bank credits, in-lieu fee programs, or permittee-responsible mitigation.