Wyoming Mechanics' Lien Statutory Compliance Auditor

Audit Wyoming preliminary notices, 20-day notice of intent to file lien, 150/120-day county recording deadlines, and 180-day district court foreclosure rules under Wyo. Stat. Title 29 Chapter 2.

Project Dates & Claimant Status

Statutory Lien Validity & Deadlines

Statutorily Valid Lien
Wyo. Stat. Ann. § 29-2-107 Mandate: "Before filing a lien, a contractor shall give twenty (20) days notice in writing to the owner... stating that he holds a claim against the property and the amount thereof." Failure to serve this notice 20 days prior to filing renders the recorded lien completely void.

Wyoming Mechanics' Lien FAQs

What is the preliminary notice rule under Wyo. Stat. § 29-2-111?

Every subcontractor and materialman must send a written notice to the owner within thirty (30) days of first providing labor or materials to the project. Failure to send this preliminary notice constitutes an absolute waiver of any mechanics lien rights under Wyoming law.

Can a contractor waive lien rights in advance in Wyoming?

No. Under Wyo. Stat. § 29-1-204, any contract provision attempting to waive lien rights prior to payment or performance is void and unenforceable as against public policy.

What is the penalty for filing a false or excessive lien in Wyoming?

Under Wyo. Stat. § 29-1-311, any person who files a lien knowing the contents to be false or groundless is liable to the owner for actual damages, statutory damages, and reasonable attorney's fees.