Audit Wyoming preliminary notices, 20-day notice of intent to file lien, 150/120-day county recording deadlines, and 180-day district court foreclosure rules under Wyo. Stat. Title 29 Chapter 2.
Every subcontractor and materialman must send a written notice to the owner within thirty (30) days of first providing labor or materials to the project. Failure to send this preliminary notice constitutes an absolute waiver of any mechanics lien rights under Wyoming law.
No. Under Wyo. Stat. § 29-1-204, any contract provision attempting to waive lien rights prior to payment or performance is void and unenforceable as against public policy.
Under Wyo. Stat. § 29-1-311, any person who files a lien knowing the contents to be false or groundless is liable to the owner for actual damages, statutory damages, and reasonable attorney's fees.