Washington RCW Chapter 60.04 Judicial Precedents
Who is required to give a Notice of Right to Claim Lien under RCW 60.04.031?
Under RCW 60.04.031, every person furnishing professional services, materials, or equipment for the improvement of real property who does not have a direct contractual relationship with the owner must give the owner or reputed owner a Notice of Right to Claim Lien. Persons contracting directly with the owner, and persons performing labor who do not furnish materials/equipment, are generally exempt.
What are the deadlines for serving the Washington Pre-Claim Notice?
For new commercial construction, notice must be served within 60 calendar days of first furnishing materials or equipment. For existing residential remodel projects (single-family residences), notice must be delivered within 10 calendar days. Late notice protects only materials or equipment delivered in the 60 days (or 10 days for residential) prior to service.
What is the recording deadline under RCW 60.04.091?
Under RCW 60.04.091, a Notice of Claim of Lien must be recorded in the county recording office where the subject real property is located not later than 90 calendar days after the claimant has ceased to furnish labor, professional services, materials, or equipment.
What is the post-recording notice to the owner under RCW 60.04.091(2)?
Within 14 calendar days of recording the claim of lien with the county auditor, the claimant must deliver or send by certified or registered mail a copy of the claim of lien to the owner or reputed owner at the owner's address. Failure to do so forfeits statutory attorney's fees and costs.
What is the statute of limitations to foreclose a Washington mechanics' lien?
Under RCW 60.04.141, no lien created by this chapter binds the property for a longer period than 8 calendar months after the claim of lien has been recorded unless an action is commenced within that time in the superior court in the county where the property is situated.