Virginia Code Title 43 Mechanics' Lien Legal Reference
What is the 150-Day Rule under Virginia Code § 43-4?
Under Virginia Code § 43-4, no lien claimant may include in the memorandum of lien any labor or materials furnished more than 150 days prior to the last day on which labor was performed or material furnished to the job. Under Virginia Supreme Court precedent (Smith Mountain Building Supply, LLC v. Windstar Properties, LLC), including any single dollar amount outside this 150-day window renders the entire lien completely void and unenforceable.
What is the recording deadline for a Virginia Mechanics' Lien Memorandum?
Under Va. Code § 43-4, the memorandum of lien must be recorded in the clerk's office of the circuit court of the county or city in which the property is located no later than 90 days from the last day of the month in which the claimant last performed labor or furnished materials, and in no event later than 90 days from the time such building, structure, or railroad is completed, or the work thereon otherwise terminated.
What is the statute of limitations to file an enforcement lawsuit in Virginia?
Under Virginia Code § 43-17, no suit to enforce any lien shall be brought after 6 months from the time when the memorandum of lien was recorded, or after 60 days from the time the building, structure, or railroad was completed or work terminated, whichever time last occurs. Failing to timely file a complaint in the circuit court extinguishes the lien entirely.
What notice must a subcontractor give to the property owner under Va. Code § 43-7?
Under Va. Code § 43-7, a subcontractor must give written notice of the amount and character of the claim to the property owner or the owner's agent along with or prior to filing the memorandum of lien. Furthermore, a subcontractor's lien is limited to the amount in which the owner is indebted to the general contractor at the time the notice is given.
Can a claimant file multiple memoranda of lien to capture work beyond 150 days?
Yes. Contractors performing long-term construction projects spanning more than 150 days frequently file periodic interim memoranda of lien to preserve their lien rights for older billing periods without violating the 150-day rule in a single final memorandum.