Calculate mandatory statutory deadlines under Vermont 9 V.S.A. Chapter 51: 180-day Town Clerk memorandum recording, 180-day Superior Court judicial action cutoff, and pre-judgment attachment requirements.

Contract & Filing History 9 V.S.A. § 1921

9 V.S.A. § 1923: 180-day recording window begins when payment is due.

Leave blank if evaluating deadline to record.

Lien is strictly limited to amount unpaid from owner to GC at notice time.

Statutory Audit Verdict Ready
180-Day Town Clerk Recording Deadline (9 V.S.A. § 1923)
--

180 days from date payment became due.

180-Day Superior Court Lawsuit Cutoff (9 V.S.A. § 1924)
--

180 days from date memorandum recorded.

Enforceable Lien Value on Real Estate
$25,000.00
Capped at $25,000 Owner Balance (§ 1921(b))
Statutory Stage Vermont Citation Deadline / Compliance
Statutory Analysis: In Vermont, a mechanics' lien requires two distinct 180-day actions: (1) recording in the Town Clerk's office within 180 days of payment due; and (2) commencing a civil action in the Superior Court with a recorded writ of attachment within 180 days of recording.

Statutory Compliance & Legal Precedents (9 V.S.A. § 1921 et seq.)

1. What is the recording deadline for a mechanics' lien in Vermont under 9 V.S.A. § 1923?
Under 9 V.S.A. § 1923, a contractor, subcontractor, or materialman asserting a mechanics' lien must record a signed, authenticated memorandum of lien in the Town Clerk's office of the town where the real estate is located within ONE HUNDRED EIGHTY (180) DAYS after payment becomes due for the labor performed or materials furnished.
2. What is the lawsuit and judicial attachment deadline under 9 V.S.A. § 1924?
Under 9 V.S.A. § 1924, within ONE HUNDRED EIGHTY (180) DAYS from the date the memorandum of lien was filed in the Town Clerk's office, the claimant must commence an action in the Vermont Superior Court and cause the real estate to be attached under Vermont Rule of Civil Procedure 4.1. If the action is not commenced or the attachment not obtained within 180 days of recording, the lien is completely extinguished.
3. How does subcontractor lien protection operate under 9 V.S.A. § 1921(b)?
Under 9 V.S.A. § 1921(b), a subcontractor or supplier who does not have a direct contract with the property owner must provide written notice to the owner stating that they intend to claim a lien. The subcontractor's lien is strictly limited to the amount unpaid and due from the owner to the general contractor at the time the owner receives the written notice.
4. Does Vermont allow an extension of the mechanics' lien?
Under 9 V.S.A. § 1924, if a judgment is obtained, the claimant must record a certified copy of the judgment in the Town Clerk's office within 30 days of the judgment becoming final. If payment is extended by contract, the memorandum must state the extension terms to maintain priority against subsequent purchasers.