Audit critical preliminary notice filings on the Utah State Construction Registry (SCR), lien recording deadlines in the County Recorder, and the 180-day judicial foreclosure Lis Pendens requirement under Utah Code Title 38, Chapter 1a.
Utah Code Ann. Title 38, Chapter 1a (Preconstruction and Construction Liens); Utah Code § 38-1a-501 (Preliminary Notice); § 38-1a-502 (Notice of Construction Lien); § 38-1a-701 (Enforcement and Foreclosure Action); Utah Residence Lien Recovery Fund Act (§ 38-11-101 et seq.).
Under Utah Code § 38-1a-501, any contractor, subcontractor, or supplier must file a Preliminary Notice on the Utah State Construction Registry (SCR at scr.utah.gov) within 20 calendar days after first commencing work or furnishing materials on the construction project. If filed after 20 days, lien rights are preserved only for labor or materials furnished starting 5 calendar days after the late filing date.
Under Utah Code § 38-1a-502, if a Notice of Completion is filed on the SCR, the mechanics lien must be recorded in the county recorder's office within 90 days after the filing of that Notice of Completion. If no Notice of Completion is filed, the lien must be recorded within 180 days after final completion of the original contract.
Under Utah Code § 38-1a-701, a claimant must file a judicial foreclosure lawsuit in the district court of the county where the property is located AND record a Lis Pendens within 180 days from the date the lien was recorded. Failure to record the Lis Pendens within 180 days renders the lien completely void and unenforceable.