Utah Mechanics Lien & SCR Statutory Auditor

Audit critical preliminary notice filings on the Utah State Construction Registry (SCR), lien recording deadlines in the County Recorder, and the 180-day judicial foreclosure Lis Pendens requirement under Utah Code Title 38, Chapter 1a.

1. Project & Role Parameters

Leave empty if preliminary notice has NOT yet been filed

2. Completion & Recording Timelines

Optional: Set if lien is already recorded to calculate Lis Pendens deadline

Statutory Audit & Required Actions

SCR Preliminary Notice Audit
SCR Preliminary Notice Deadline (20 Days): --
SCR Filing Status & Protection: --
Governing Lien Recording Deadline Rule: 180 Days (No NOC)
Deadline to Record Mechanics Lien: --
Mandatory Copy to Owner (§ 38-1a-701): Within 30 Days of Recording
Lawsuit & Lis Pendens Filing Deadline: --

Statutory Process Roadmap

1
File Preliminary Notice on SCR
Due: --
Utah Code § 38-1a-501: File on scr.utah.gov within 20 days of first work.
2
Record Notice of Construction Lien
Deadline: --
Record in County Recorder's Office where real property is situated.
3
Certified Mail Notice to Owner
Within 30 Days of Recording
Send copy of recorded lien by certified mail to property owner (§ 38-1a-701).
4
District Court Lawsuit & Lis Pendens
Deadline: --
Utah Code § 38-1a-701: Must commence foreclosure & record Lis Pendens within 180 days.
Statutory Notice: Failure to strictly adhere to the Utah State Construction Registry (SCR) electronic filing requirements or the 180-day Lis Pendens recording deadline completely extinguishes and voids the lien.
Statutory Authority & Compliance References:

Utah Code Ann. Title 38, Chapter 1a (Preconstruction and Construction Liens); Utah Code § 38-1a-501 (Preliminary Notice); § 38-1a-502 (Notice of Construction Lien); § 38-1a-701 (Enforcement and Foreclosure Action); Utah Residence Lien Recovery Fund Act (§ 38-11-101 et seq.).

🏠 Home Hub

Frequently Asked Questions Regarding Utah Mechanics Liens

When must a Preliminary Notice be filed on the Utah State Construction Registry (SCR)?

Under Utah Code § 38-1a-501, any contractor, subcontractor, or supplier must file a Preliminary Notice on the Utah State Construction Registry (SCR at scr.utah.gov) within 20 calendar days after first commencing work or furnishing materials on the construction project. If filed after 20 days, lien rights are preserved only for labor or materials furnished starting 5 calendar days after the late filing date.

What is the deadline to record a Mechanics Lien in Utah?

Under Utah Code § 38-1a-502, if a Notice of Completion is filed on the SCR, the mechanics lien must be recorded in the county recorder's office within 90 days after the filing of that Notice of Completion. If no Notice of Completion is filed, the lien must be recorded within 180 days after final completion of the original contract.

How long do you have to foreclose a mechanics lien in Utah?

Under Utah Code § 38-1a-701, a claimant must file a judicial foreclosure lawsuit in the district court of the county where the property is located AND record a Lis Pendens within 180 days from the date the lien was recorded. Failure to record the Lis Pendens within 180 days renders the lien completely void and unenforceable.