Statutory Retainage Analysis & Deadlines
RETAINAGE NOTICE TIMELY & FULLY PERFECTED
Statutory 10% Retainage Fund Required (§ 53.101)
$150,000.00
10% of $1,500,000 prime contract price
Retainage Notice Statutory Deadline (§ 53.057)
October 15, 2026 (Timely)
15th day of 3rd month after July first furnishing
Retainage Lien Affidavit Recording Deadline (§ 53.052(d))
February 15, 2027
15th day of 3rd month following November completion
Owner Personal Liability Exposure (§ 53.105)
$0.00 (Fund Withheld)
Lien attaches to 10% retainage fund held by owner
Statutory Assessment: Claimant served retainage notice within the 15th-day-of-the-3rd-month window under Tex. Prop. Code § 53.057. Record Retainage Lien Affidavit before February 15, 2027.
Frequently Asked Questions (Texas Property Code Chapter 53)
What is the mandatory 10% statutory retainage requirement under Texas Property Code § 53.101?
Under Texas Property Code § 53.101, during the progress of work under an original contract for which a mechanics' lien may be claimed, and for 30 calendar days after the work is completed, the property owner MUST retain either: (1) 10 percent of the contract price of the work to the owner; or (2) 10 percent of the value of the work, measured by the proportion that the work done bears to the work to be done. This retained fund exists specifically to protect derivative claimants (subcontractors and suppliers) who are not paid by the prime contractor.
What notice must a subcontractor send to secure a claim against the retainage fund under § 53.057?
Under Texas Property Code § 53.057 (as modernized by House Bill 2237), a derivative claimant must provide written notice of a contractual retainage agreement to the owner and the original contractor not later than the 15th day of the 3rd month following the month in which the claimant first furnished labor or materials under the contract (or within 30 days after the claimant's agreement provides for retainage, or after the original contract was completed, terminated, or abandoned, whichever date is earliest).
What is the deadline to file a Retainage Lien Affidavit under Texas Property Code § 53.052(d)?
Under Texas Property Code § 53.052(d), a claimant claiming a lien for retainage must file an affidavit of lien with the county clerk in the county where the property is located not later than the 15th day of the 3rd month after the month in which the original contract was completed, terminated, or abandoned. Timely recording secures a direct statutory lien against the property and the owner's retainage fund under § 53.103.
What happens if an owner fails to withhold the mandatory 10% statutory retainage under § 53.105?
Under Texas Property Code § 53.105, if the property owner fails or refuses to withhold the mandatory 10% retainage during construction and for 30 days post-completion, the owner is PERSONALLY LIABLE to any valid claimant who timely perfected their retainage lien, up to the full amount that the owner was required to retain. Furthermore, the claimant's lien attaches directly to the owner's real property to secure payment of this liability.
What major changes did Texas House Bill 2237 make to mechanics' lien notices?
Effective January 1, 2022, Texas HB 2237 substantially streamlined Texas mechanics' lien practice: (1) It eliminated the burdensome second-tier 2nd-month notice for retainage; (2) Standardized statutory notice forms under § 53.056 and § 53.057; (3) Explicitly allowed service by certified mail, registered mail, or any form of traceable private carrier; and (4) Harmonized commercial and residential deadlines into the standardized '15th day of the month' framework.