Calculate South Dakota mechanics lien filing deadlines under the 120-day rule (SDCL § 44-9-15), itemized statements, and 30-day demand foreclosure suits under SDCL § 44-9-26.
| Statutory Requirement | Status / Metric | SDCL Citation |
|---|
| Maximum Statutory Recording Window: | 120 Days (SDCL § 44-9-15) |
| Remaining Filing Days (if unfiled): | 45 Days Remaining |
| Foreclosure Acceleration: | Standard 6-Year Window |
| Register of Deeds Jurisdiction: | County of Improved Property |
Under South Dakota Codified Laws (SDCL) § 44-9-15, a lien ceases at the end of 120 days after the date on which the last item of work, labor, or materials was furnished, unless the lien claimant files a verified lien statement with the register of deeds of the county in which the improved property is situated.
Under SDCL § 44-9-16, the lien statement must set forth: (1) notice of intention to claim and hold a lien, (2) the amount owing and demand, (3) a description of the property improved, (4) the name of the owner, (5) the first and last dates of furnishing labor or materials, and (6) an itemized account of the work done or materials provided, verified by oath.
Under SDCL § 44-9-24, an action to enforce a mechanics lien must be commenced within 6 years after the date of the last item of work or material furnished. However, under SDCL § 44-9-26, the property owner may serve a written demand requiring the lienholder to commence suit, in which case the lienholder must commence foreclosure within 30 days or the lien is forfeited.
Under SDCL § 44-9-6, any person furnishing labor or materials to a contractor or subcontractor may serve a written notice upon the owner, notifying the owner of the work and estimated cost. The owner may then withhold sufficient funds from the prime contractor to pay the claim.