South Carolina Statutory Construction Law

South Carolina Mechanics' Lien § 29-5 Auditor

Audit South Carolina verified statement recording windows (§ 29-5-90), 6-month lis pendens suit deadlines (§ 29-5-120), and § 29-5-23 Notice of Project Commencement defenses.

🏗️ Project & Claim Information
Caps subcontractor lien recovery under S.C. Code § 29-5-40.
⚖️ Statutory Deadlines & Recovery Cap
LIEN RIGHTS FULLY PRESERVED: All preliminary notice standards met. Claimant is eligible to record verified statement under S.C. Code § 29-5-90.
90-Day Recording Deadline (§ 29-5-90) May 16, 2026
6-Month Suit & Lis Pendens Deadline Aug 15, 2026
Enforceable Dollar Lien Cap: $62,500.00
§ 29-5-23 Commencement Defense: Protected (Notice Furnished)
Owner Defense of Payment Shield: Sufficient Owner Funds ($75,000)
Days Remaining to Record: Calculated
S.C. Code Ann. § 29-5-90: "Such a lien shall be dissolved unless the person desiring of availing himself thereof, within ninety days after he ceases to labor on or furnish labor or materials... serves upon the owner... and files in the office of the register of deeds... a just and true account."

South Carolina Litigation Checklist

  • Serve verified statement upon property owner via Sheriff or Certified Mail prior to recording.
  • File verified statement with Register of Deeds in county where land is located.
  • Simultaneously file summons, complaint, and formal Lis Pendens in Court of Common Pleas before 6-month deadline.

Statutory Framework: South Carolina Mechanics' Lien Law

South Carolina Code Title 29, Chapter 5 (§§ 29-5-10 through 29-5-440) establishes a rigid statutory procedure to secure debts for labor and materials furnished for property improvements. Because mechanics' liens encumber real property title without prior judicial hearing, South Carolina courts enforce strict compliance with every statutory timeline.

The 90-Day Recording Window (§ 29-5-90)

Under S.C. Code Ann. § 29-5-90, the lien claimant has exactly 90 calendar days from the date they last performed labor or supplied materials to:

  1. Serve a copy of the verified notice and certificate of lien upon the property owner (or person in possession); and
  2. File the certificate of lien with the Register of Deeds (or Clerk of Court in counties without a Register) where the real estate is located.

Failure to record within 90 days completely dissolves the lien by operation of law. Unlike certain other states, South Carolina provides no statutory grace period or equitable tolling for recording delays.

The 6-Month Foreclosure & Lis Pendens Rule (§ 29-5-120)

Recording the lien is merely a provisional step. Under S.C. Code Ann. § 29-5-120, the lien is dissolved unless an action to enforce the lien is commenced in the Court of Common Pleas within 6 months after the claimant ceased labor or materials. Critically, South Carolina requires the contemporaneous filing of a formal Notice of Lis Pendens. If the complaint is filed but the lis pendens is omitted, the lien is statutorily extinguished.

Notice of Project Commencement (§ 29-5-23)

To protect owners and general contractors from hidden remote liens, South Carolina enacted § 29-5-23. If an owner or GC files a Notice of Project Commencement with the Register of Deeds within 15 days of breaking ground and posts a copy on the jobsite, 2nd-tier subcontractors and remote suppliers MUST deliver a written "Notice of Furnishing Labor or Materials" to the general contractor. If a remote sub fails to serve this notice, their lien is restricted to the amount the GC owes to the 1st-tier sub, leaving remote subs unshielded if the 1st-tier sub defaulted.

Frequently Asked Questions: South Carolina Mechanics' Liens

What is the recording deadline for a mechanics' lien in South Carolina under § 29-5-90?
Under S.C. Code Ann. § 29-5-90, a verified notice and statement of lien must be served upon the property owner and recorded in the Office of the Register of Deeds (or Clerk of Court) in the county where the property is located within 90 days after the claimant ceases to labor on or furnish labor or materials for the building or structure.
What is the deadline to file a lien foreclosure lawsuit and lis pendens in South Carolina?
Under S.C. Code Ann. § 29-5-120, a suit to enforce the mechanics' lien must be commenced AND a notice of lis pendens filed within 6 months after the claimant ceases to labor or furnish materials. If the lawsuit and lis pendens are not filed within this 6-month window, the lien is statutorily dissolved.
How does a Notice of Project Commencement affect remote subcontractors under § 29-5-23?
Under S.C. Code Ann. § 29-5-23, if the owner or general contractor files a Notice of Project Commencement with the Register of Deeds within 15 days of starting work and posts it on site, remote 2nd-tier subcontractors and suppliers MUST deliver a Notice of Furnishing Labor or Materials to the general contractor to preserve full lien rights. Otherwise, their lien is limited to amounts owed by the GC to the 1st-tier sub.
Can a subcontractor lien exceed the owner's remaining contract balance to the general contractor?
Under S.C. Code Ann. § 29-5-40, the aggregate liens of subcontractors cannot exceed the amount remaining unpaid by the owner to the general contractor at the time the owner receives written notice of the lien claim, unless the owner agreed in writing to be personally responsible.