South Carolina Mechanics' Lien Compliance Auditor

Audit South Carolina mechanics lien deadlines under S.C. Code § 29-5-10 et seq.: 90-day recording deadline, service on owner, Notice of Furnishing safe harbor, and 6-month foreclosure lawsuit limitation.

Project & Recording Dates

Statutory Validity & Timelines

Timely Recorded
Crucial SC Deadline Rule: Under S.C. Code § 29-5-120, the 6-month foreclosure lawsuit deadline runs from the date labor ceased, NOT from the recording date! Failure to file lis pendens and complaint within 6 months of ceasing work completely dissolves the lien.

South Carolina Mechanics' Lien FAQs

Can an unlicensed contractor file a mechanics lien in South Carolina?

No. Under South Carolina law (S.C. Code § 40-11-370 and § 29-5-15), any contractor or subcontractor who is required to be licensed by the South Carolina Contractor's Licensing Board and performs work without a valid license cannot enforce a mechanics lien or bring an action to recover on the contract.

What is the Notice of Project under S.C. Code § 29-5-23?

If the owner or contractor files a formal 'Notice of Project' with the clerk of court within 15 days of commencement and posts it at the job site, remote subcontractors and suppliers must serve a Notice of Furnishing to preserve their full lien rights.

Are attorney's fees recoverable in South Carolina lien actions?

Yes. Under S.C. Code § 29-5-10(a) and § 29-5-20, the prevailing party in an action to enforce or vacate a mechanics lien is statutorily entitled to recover reasonable attorney's fees and court costs, provided the claimant made a timely settlement offer.