Calculate Rhode Island mechanics' lien deadlines under R.I. Gen. Laws Chapter 34-28: audit the retroactive 200-day Notice of Intention lookback window (§ 34-28-4), 40-day Superior Court petition cutoff (§ 34-28-10), and 7-day lis pendens rules.
§ 34-28-4: Lien only protects work done within 200 days PRIOR to recording.
Work older than 200 days is forfeited and cannot be liened under § 34-28-4(a).
40 calendar days from recording Notice of Intention.
| Rhode Island Mandate | R.I. Gen. Laws Section | Deadline / Status |
|---|