Pennsylvania Mechanics' Lien Law (49 P.S. § 1101) Auditor

Complete procedural deadline calculator for Pennsylvania mechanics' liens under 49 P.S. § 1101 et seq. Audits 30-day preliminary subcontractor notice (§ 1501), 6-month prothonotary recording deadlines (§ 1502), 1-month service, and 2-year writ of scire facias enforcement.

Claimant & Work Milestones

Clock runs strictly from completion; warranty or minor touch-up work does not extend.

Statutory Milestones & Enforceability

LIEN RIGHTS ACTIVE
Formal Notice Cutoff
--
6-Month Prothonotary Limit
--
Days to File Claim
--
2-Year Scire Facias Expiry
--

Pennsylvania Mechanics' Lien Law Statutory Architecture

What notice must a subcontractor provide before filing a mechanics' lien in Pennsylvania?
Under 49 P.S. § 1501(b), a subcontractor must serve formal written notice of intention to file a lien claim upon the property owner at least 30 calendar days BEFORE filing the lien claim with the prothonotary. This notice must state the claimant's intent, the nature of labor or materials, date when furnished, and the amount due.
What is the deadline to file a mechanics' lien claim in Pennsylvania?
Under 49 P.S. § 1502(a)(1), to perfect a lien, every claimant must file a claim with the prothonotary of the Court of Common Pleas within 6 months after the completion of the claimant's work or furnishing of materials.
What post-filing service and affidavit requirements apply?
Under 49 P.S. § 1502(a)(2), the claimant must serve written notice of the filing upon the owner within 1 month after filing the claim, AND file an affidavit of service of notice, or the acceptance of service, within 20 days after service. Failure to serve notice or file the affidavit within the specified times forfeits the lien rights completely.
When does a Pennsylvania mechanics' lien expire if no lawsuit is commenced?
Under 49 P.S. § 1701(a), an action to obtain judgment upon a claim filed (a writ of scire facias) must be commenced within 2 years from the date of filing the lien claim, and final judgment must be entered within 5 years.
How does the Pennsylvania State Construction Notices Directory affect lien rights?
Under 49 P.S. § 1501.3, for registered construction projects with a contract value of $1,500,000 or more where the owner or prime contractor files a Notice of Commencement on the PA State Construction Notices Directory, subcontractors and suppliers must file a Notice of Furnishing within 45 calendar days of first performing work or supplying materials. Failure to file this Notice of Furnishing forfeits mechanics' lien rights.
Can a subcontractor waive mechanics' lien rights in advance in Pennsylvania?
Under 49 P.S. § 1401, advance waivers of mechanics' lien rights are against public policy and VOID for subcontractors and suppliers, UNLESS the contractor posts a payment bond protecting subcontractors, or in residential projects where the owner has paid the full contract price to the general contractor.