Statutory Lien Analysis & Critical Deadlines
100% OF CLAIM PROTECTED UNDER ORS 87
Notice of Right to Lien Delivery (ORS 87.021)
Timely Delivered Within 8 Days
No retroactive lookback forfeiture. Full protection confirmed.
Lien Recording Statutory Deadline (ORS 87.035)
January 29, 2027 (75 Days)
Must record Claim of Lien in county recording office
Court Foreclosure Lawsuit Bar (ORS 87.055)
120 Days Post-Recording
Lien expires automatically if foreclosure lawsuit not filed within 120 days
Statutory Assessment: Claimant satisfies preliminary delivery rules under ORS 87.021. Record Claim of Lien within 75 days of completion and file foreclosure lawsuit within 120 days.
How strictly do Oregon courts enforce the 8-business-day delivery window?
Oregon courts enforce the 8-day notice rule with strict statutory precision. In Sun Solutions, Inc. v. Brant (2015) and A-C Construction, Inc. v. Bakke Corp. (1998), the Oregon Court of Appeals confirmed that construction liens are purely creatures of statute in derogation of common law. Consequently, if a subcontractor or material supplier fails to deliver the Notice of Right to a Lien within the statutory lookback window, courts have no equitable power to relax the 8-day bar. Any claim for work performed prior to the 8-day period is permanently dismissed.
Frequently Asked Questions (Oregon ORS Chapter 87)
When must the Notice of Right to a Lien be delivered under Oregon ORS 87.021?
Under Oregon Revised Statutes ORS 87.021, any person performing labor, providing professional services, or furnishing materials or equipment for an improvement—who does not contract directly with the property owner—must deliver a written Notice of Right to a Lien to the owner. The notice may be delivered at any time during the construction, but it only preserves lien rights for labor and materials furnished during the 8 business days immediately preceding the date the notice is delivered or mailed, and for all work furnished thereafter.
What are the consequences of delivering the Oregon preliminary notice late?
Under ORS 87.021(1), if a material supplier or subcontractor delivers the Notice of Right to a Lien late (for example, 30 days after starting deliveries), all materials and labor furnished prior to the 8-business-day lookback window are completely and permanently barred from lien protection. The claimant can only enforce a construction lien for materials furnished within the 8 business days prior to notice service and going forward.
What is the residential Information Notice to Owner requirement under ORS 87.093?
Under ORS 87.093, a general or prime contractor who enters into a direct contract with an owner for residential construction or remodeling exceeding $2,000 must deliver a statutory 'Information Notice to Owner About Construction Liens' at the time of signing the contract. If the contract was originally under $2,000 but subsequent change orders cause the total price to exceed $2,000, the contractor must deliver the Information Notice within 5 days of knowing the contract will exceed $2,000. Failure to deliver this notice completely forfeits the contractor's right to claim a lien.
What are the deadlines to record and foreclose an Oregon construction lien?
Under ORS 87.035, a claimant must record a Claim of Lien in the county recording office within 75 calendar days after the claimant ceases to perform labor or furnish materials, or 75 days after completion of construction, whichever is earlier. Under ORS 87.055, an action to foreclose the construction lien must be commenced in circuit court within 120 calendar days after the date the lien was recorded; otherwise, the lien expires automatically.