Audit mechanics' and materialmen's construction lien perfection deadlines under North Dakota Century Code Chapter 35-27 (N.D.C.C. § 35-27-01 et seq.). Compute the 15-day pre-lien notice of intent, 90-day recording deadline in the central indexing system, priority over encumbrances, and 3-year foreclosure limitation.

Statutory Authority: N.D.C.C. Chapter 35-27 (North Dakota Construction Lien Law)

Construction Lien Parameters

Primary Priority
$
90-day recording deadline (§ 35-27-13)
15-day mandatory waiting period (§ 35-27-05)

Lien Perfection Status

ENFORCEABLE
Priority & Perfection Level
SENIOR PRIORITY
Recorded within 90 days; takes priority over subsequent encumbrances
90-Day Recording Deadline
45 Days Remaining
Must file in Central Indexing System (CIS) / County Recorder
Statutory Prerequisite Status
15-Day Pre-Lien Notice (§ 35-27-05) Satisfied (18 Days)
90-Day Recording Window (§ 35-27-13) 45 Days Remaining
Lien Priority against Encumbrancers Superior Priority
Foreclosure Deadline (§ 35-27-25) 3 Years from Recording
Maximum Enforceable Claim $45,000.00

North Dakota Century Code Chapter 35-27 Statutory Guidelines

What is the pre-lien notice requirement in North Dakota?
Under N.D.C.C. § 35-27-05, any person who furnishes labor, materials, or services must serve a written Notice of Intent to Claim Lien on the property owner by certified mail or personal service at least 15 days before recording the construction lien.
What is the recording deadline for a construction lien in North Dakota?
Under N.D.C.C. § 35-27-13, to preserve full statutory priority against subsequent purchasers and encumbrancers, a construction lien must be recorded in the central indexing system within 90 days after the last item of labor, materials, or services was furnished.
Can a construction lien be filed after 90 days in North Dakota?
Yes. Under N.D.C.C. § 35-27-14, a claimant may record a lien after the 90 days have expired, but the lien will be subordinate and inferior to rights acquired in good faith by purchasers or encumbrancers whose rights attached prior to the actual recording of the lien.
What is the deadline to foreclose a construction lien in North Dakota?
Under N.D.C.C. § 35-27-25, an action to enforce and foreclose a construction lien must be commenced within 3 years after the date the lien was recorded. If the owner serves a written demand to sue, the deadline is shortened to 30 days.