NY Lien Law § 38 Mechanics Liens

New York Lien Law § 38 Itemized Statement Auditor

Audit compliance with written demands for itemized statements of mechanics liens under New York Lien Law § 38, calculating the strict 5-day statutory response deadline, itemization sufficiency, and court cancellation risk.

Demand & Claim Particulars

Strict 5 calendar days begin the day after receipt under NY General Construction Law § 20.
Uncompleted and extras claims require meticulous hour/unit breakdowns.
Solow standard requires itemized labor hours and rates.
Must specify unit prices and quantities of materials actually incorporated.
Must be verified under oath.
Failure to obey court order triggers mandatory lien discharge.

Section 38 Audit Findings Compliant

Statutory 5-Day Response Deadline: Calculated on Date Entry
Days Remaining to Serve Statement: --
Itemization Sufficiency Rating: Sufficient (Solow Standard)
Risk of Supreme Court Lien Cancellation: LOW
Mandatory Oath / Verification: SATISFIED
New York Lien Law § 38 Analysis: Statement complies with statutory verified itemization requirements.

Lienor Protection Protocols:

  • Serve verified itemized statement via certified mail / process server.
  • Retain proof of delivery to defend against frivolous discharge petitions.
  • Maintain contemporaneous timesheets and supplier delivery receipts.

Complete Statutory Guide to New York Lien Law § 38

Under Section 38 of the New York Lien Law, an owner or prime contractor against whose property or contract a notice of mechanics lien has been filed possesses the statutory right to demand a verified itemized statement from the lienor. This mechanism is designed to prevent inflated or frivolous liens by forcing the claimant to substantiate their claims under penalty of perjury.

1. The Strict 5-Day Response Rule

The statute provides that the lienor shall, within five (5) days after written demand, deliver to the demanding party a statement in writing setting forth the items of labor and/or material and the value thereof which make up the amount for which he claims a lien. In practice, failure to respond within 5 days opens the door for immediate judicial intervention in the New York Supreme Court.

2. Judicial Sufficiency Standards (The Solow Doctrine)

In the seminal decision Matter of Solow v. Bethlehem Steel Corp., 33 A.D.2d 444, 308 N.Y.S.2d 580 (1st Dept. 1970), the Appellate Division established the criteria for itemization sufficiency:

3. Court Petitions and Lien Cancellation Mechanism

If the lienor fails to comply within 5 days, or provides a deficient statement, the owner may move under Section 38 for an order directing compliance. If the lienor fails to comply with the court order within the time fixed therein, the court shall make an order cancelling and discharging the lien of record.

Frequently Asked Questions Regarding NY Lien Law § 38

What is the statutory deadline to respond to a NY Lien Law § 38 demand? +
Under NY Lien Law § 38, a lienor must deliver a verified itemized statement within five (5) days after receipt of a written demand from the property owner or contractor.
What specific details must be included in a NY Lien Law § 38 itemized statement? +
Under established New York case law (Matter of Solow v. Bethlehem Steel Corp. and Plain Avenue Storage v. Town of Huntington), the statement must set forth: (1) specific items and quantities of labor performed, employee classifications, hourly wage rates, and dates performed; (2) specific materials furnished, quantities, unit prices, and delivery dates; and (3) the terms of the underlying contract and agreed change orders under which the work was performed.
What happens if a lienor fails to provide an itemized statement under NY Lien Law § 38? +
If a lienor fails to respond within 5 days, or provides an inadequate statement, the demanding owner or contractor may petition the New York Supreme Court for an order directing compliance within a specified time (typically 10-20 days). If the lienor fails to comply with the court order, the court must issue an order cancelling and discharging the mechanics lien entirely.
Does NY Lien Law § 38 require an itemized statement for an uncompleted lump-sum contract? +
For fully completed lump-sum express contracts, detailed itemization is generally not required if the agreed contract price is established. However, where a contract is uncompleted, terminated prior to completion, or where claims involve disputed extra work and change orders on a quantum meruit basis, strict itemization of labor and materials is mandatory.