Audit New Mexico mechanics lien preliminary notice deadlines (60-day rule under NMSA § 48-2-2.1), 120-day original contractor vs 90-day subcontractor county recording deadlines, and the 2-year district court foreclosure statute of limitations.
New Mexico Statutes Annotated (NMSA 1978), Chapter 48, Article 2; NMSA § 48-2-2.1 (Preliminary Notice requirements for sub-tier claimants); § 48-2-6 (Time for filing lien claim in county clerk's office); § 48-2-10 (Duration of lien and two-year foreclosure limitation).
Under NMSA 1978 § 48-2-2.1, for commercial projects or residential projects where the contract amount exceeds $5,000, subcontractors and material suppliers who have no direct contract with the owner or original contractor must serve a Preliminary Notice on the owner and general contractor within sixty (60) days of first furnishing work or materials. Late notice covers only work provided in the 30 days preceding service and thereafter.
Under NMSA 1978 § 48-2-6, an original contractor (holding a direct contract with the owner) has one hundred twenty (120) days after completion of the contract to file a claim of lien with the county clerk. Subcontractors, laborers, and materialmen must file their claim of lien within ninety (90) days after completion of the building, improvement, or structure.
Under NMSA 1978 § 48-2-10, a mechanics lien remains valid for two (2) years after the date the lien was recorded in the county clerk's office. The claimant must initiate a foreclosure action in the district court within this 2-year period, otherwise the lien automatically expires and becomes void.