New Jersey Construction Lien Law (N.J.S.A. § 2A:44A) Auditor

Complete statutory calculator and compliance auditor for New Jersey construction liens. Calculates commercial 90-day recording limits, residential 60-day NUB & AAA arbitration milestones, and the 1-year enforcement lawsuit deadline.

Project & Work Timeline

Clock starts strictly on the last date of actual physical work or delivery (§ 2A:44A-6). Punch list/warranty work does not extend deadline.
Lien fund cap: under § 2A:44A-9, a sub's lien cannot exceed owner's unpaid balance to prime contractor.

Statutory Deadlines & Enforceability

LIEN RIGHTS ACTIVE
Lien / NUB Deadline
--
Days Remaining
--
1-Year Lawsuit Expiry
--
Effective Lien Fund Cap
$84,500

New Jersey Construction Lien Law (N.J.S.A. § 2A:44A) Q&A

What is the deadline to record a commercial construction lien in New Jersey?
Under N.J.S.A. § 2A:44A-6, for non-residential (commercial) construction, the Construction Lien Claim must be filed and recorded with the county recording officer within 90 calendar days from the date the claimant last performed work or provided services or materials pursuant to a contract.
What special procedure applies to residential construction liens in New Jersey?
Under N.J.S.A. § 2A:44A-21, residential construction claims require a strict multi-step arbitration process: (1) file a Notice of Unpaid Balance and Right to File Lien (NUB) within 60 calendar days of last work, (2) serve the NUB on the owner within 10 calendar days, (3) file a demand for expedited arbitration with the American Arbitration Association (AAA) within 10 calendar days of filing the NUB, (4) receive the arbitrator's determination within 30 days, and (5) record the final Construction Lien Claim within 10 calendar days of receiving the arbitrator's award.
What is the deadline to serve the recorded lien claim on the property owner?
Under N.J.S.A. § 2A:44A-7, within 10 business days following the filing of the lien claim, the claimant must serve a copy of the lien claim upon the owner of the real property by personal service or certified mail, return receipt requested, together with a copy marked with the recording date by the county clerk.
When does a New Jersey construction lien expire if no lawsuit is filed?
Under N.J.S.A. § 2A:44A-14, an action to enforce a lien claim (lawsuit to foreclose) must be commenced in the New Jersey Superior Court within 1 year from the date the claimant last performed work or delivered materials, NOT 1 year from the recording date. Failing to file within 1 year forfeits all lien rights.