Audit 120-day lien duration, subcontractor notice prerequisites, writ of summons attachment deadlines, and priority under New Hampshire RSA Chapter 447.
New Hampshire does not have a simple 'document recording' lien system. A claimant cannot preserve their lien simply by recording an affidavit with the registry of deeds. Perfection requires filing an action in superior court with an ex parte or noticed petition for writ of attachment within 120 days of last work.
Under RSA 447:6, a subcontractor who gives notice after furnishing labor or materials has a lien only to the extent of any amount then due or that may thereafter become due to the contractor from the owner. If the owner has already paid the prime contractor in full, the subcontractor has no lien rights against the property.
Under RSA 447:8, any subcontractor or person giving notice under RSA 447:5 must give to the owner or agent an account in writing of the labor performed or materials furnished once in every 30 days during the project to preserve continuous lien priority.