Nevada Construction Law

Nevada Mechanics' & Materialmen's Lien Auditor (NRS Chapter 108)

Precision statutory deadline and perfection tracking under NRS § 108.221 through § 108.246. Calculate mandatory preliminary notices, recording deadlines under Notice of Completion, and district court foreclosure limitations.

Project Dates & Claimant Status

Under NRS § 108.245, lower-tier claimants must serve Notice of Right to Lien.
Residential requires 15-day pre-lien notice of intent.
Serves as trigger for 31-day Notice of Right to Lien.
Leave blank if not yet served.
Standard 90-day recording countdown trigger.
Used to calculate 6-month lawsuit foreclosure deadline.

Statutory Deadlines & Risk Status

Perfection Schedule Active

All statutory deadlines computed based on NRS Chapter 108 mandates.

--
Notice of Right to Lien (31 Days)
--
Lien Recording Deadline
--
Lawsuit Deadline (6 Months)
--
Pre-Lien Intent Notice

Critical Nevada Practice Rules

  • 31-Day Rule: NRS § 108.245 requires serving Notice of Right to Lien within 31 days. Late service protects only labor/materials furnished within 31 days prior to actual service.
  • Service of Lien: Under NRS § 108.227, a copy of the recorded Notice of Lien must be served personally or by certified mail on the owner within 30 days after recording.
  • Lis Pendens: Concurrently with filing the district court foreclosure complaint, claimant must record a Notice of Pendency under NRS § 108.239.

Frequently Asked Questions: Nevada NRS Chapter 108

What is the effect of late service of the Notice of Right to Lien under NRS 108.245?
Unlike states where failing to give preliminary notice completely extinguishes lien rights, Nevada provides a 'rolling' protection. If a claimant serves notice after 31 days, the lien remains valid for labor, equipment, and materials furnished within the 31 days immediately preceding the date of service and anytime thereafter. Work performed prior to that 31-day lookback window is permanently excluded.
Can an owner shorten the 90-day recording deadline in Nevada?
Yes. Under NRS § 108.228, an owner may record a Notice of Completion in the county recorder's office and deliver a copy by personal delivery or certified mail to all known claimants. If properly recorded and served, the deadline to record a Notice of Lien is shortened from 90 days to 40 days after the Notice of Completion is recorded.
What specific statutory warnings must be included in a Nevada Notice of Lien?
Under NRS § 108.226, the Notice of Lien must be verified by oath, set forth the legal property description, name of the owner, statement of the demand after deducting all just credits and offsets, and the name of the person by whom the claimant was employed or to whom materials were furnished. For residential properties, the 15-day pre-lien notice is mandatory.
What happens if a foreclosure action is not filed within 6 months?
Under NRS § 108.233, the lien automatically expires and becomes void. The owner may demand a discharge and release of lien under NRS § 108.244. If the claimant fails to release an expired or frivolous lien within 10 days of written demand, the owner is entitled to damages, court costs, and reasonable attorney's fees.