Nebraska Construction Lien Act Statutory Auditor

Audit Nebraska Construction Lien Act statutory requirements under Neb. Rev. Stat. § 52-125 et seq. Calculate the 120-day Register of Deeds recording deadline, mandatory 10-day owner notice, 2-year judicial foreclosure statute of limitations, and 30-day owner demand accelerations.

1. Project & Furnishing Dates

Leave empty if lien has not yet been recorded

2. Owner Notices & Demand to Sue

Statutory Audit & Procedural Deadlines

Lien Recording Window Open
120-Day Recording Deadline (§ 52-137): --
Days Remaining to Record Lien: -- Days
Mandatory Copy to Owner Deadline (§ 52-135): Within 10 Days of Recording
Governing Foreclosure Lawsuit Rule: 2 Years (§ 52-140)
Final Foreclosure Lawsuit Deadline: --
Lien Validity Status: Active & Enforceable
Statutory Analysis: Under Neb. Rev. Stat. § 52-137, a lien must be recorded in the county Register of Deeds within 120 calendar days after the claimant's last date of work. Once recorded, the lien remains enforceable for up to 2 years unless the owner invokes the 30-day demand-to-sue procedure.
Statutory Authority & Compliance References:

Nebraska Construction Lien Act, Neb. Rev. Stat. § 52-125 through § 52-159; § 52-135 (Copy of recorded lien to contracting owner); § 52-137 (120-day recording deadline); § 52-140 (Two-year judicial foreclosure duration and 30-day demand to institute action); § 52-145 (Notice of Commencement effects).

🏠 Home Hub

Frequently Asked Questions Regarding Nebraska Construction Liens

What is the deadline to record a construction lien in Nebraska?

Under Neb. Rev. Stat. § 52-137, a claimant must record a lien in the office of the Register of Deeds in the county where the real estate is located no later than one hundred twenty (120) calendar days after the claimant's final furnishing of services or materials.

Must a copy of the recorded lien be sent to the owner in Nebraska?

Yes. Under Neb. Rev. Stat. § 52-135, the claimant must send a copy of the recorded lien to the contracting owner within ten (10) calendar days after recording the lien. Failure to serve the copy may expose the claimant to statutory damages and costs.

How long is a construction lien effective in Nebraska before a lawsuit must be filed?

Under Neb. Rev. Stat. § 52-140, a construction lien is effective for two (2) years after recording. A judicial foreclosure action must be filed in the district court within this two-year period; however, if the owner serves a written demand to institute action, the claimant must file the lawsuit within thirty (30) days of receipt or the lien is extinguished.