Montana Construction Lien & Notice Auditor

MCA Title 71 Ch. 3 Part 5 Preliminary Notice, Recording Windows & Foreclosure

Project & Furnishing Timeline

MCA § 71-3-531

Statutory Deadlines & Lien Enforceability

Auditing...
Preliminary Notice Status (20-Day Limit): Timely Served
County Recording Deadline (90 Days): Calculating...
Days Elapsed from Final Work: 0 Days
Lien Recording Validity: VALID & TIMELY
Two-Year Foreclosure Expiration Date: Calculating...
Days Remaining to File Lawsuit: 730 Days
Statutory Attorney's Fee Recovery: Available (MCA § 71-3-124)
Enforceable Lien Security Amount: $45,000.00
Audit complete.

Frequently Asked Questions: Montana Construction Liens

Who must serve a Notice of Right to Claim a Lien in Montana (MCA § 71-3-531)?
Under MCA § 71-3-531, subcontractors and material suppliers who do not contract directly with the property owner must serve a Notice of Right to Claim a Lien on the owner within 20 days of first furnishing labor or materials. Direct general contractors, wage earners, and suppliers to commercial projects of more than 5 residential units are statutorily exempt from this notice.
What is the consequence of serving a late Notice of Right to Claim a Lien in Montana?
Under MCA § 71-3-531(4), if notice is served after 20 days, the lien remains valid but only covers services, labor, or materials furnished within the 20 days immediately preceding the date the notice was given and services furnished thereafter. All work performed prior to that 20-day retroactive window is permanently forfeited.
What is the recording deadline for a Montana construction lien under MCA § 71-3-535?
Under MCA § 71-3-535, a construction lien must be recorded in the county clerk and recorder's office within 90 days after the claimant's final furnishing of services or materials, or within 90 days after the owner records and publishes a valid Notice of Completion.
What is the statute of limitations to foreclose a Montana construction lien (MCA § 71-3-562)?
Under MCA § 71-3-562, an action to enforce and foreclose a construction lien must be commenced in district court within two years from the date the lien was filed with the county clerk and recorder. The prevailing party is statutorily entitled to recover reasonable attorney's fees under MCA § 71-3-124.