Audit Montana construction lien deadlines under MCA Title 71 Chapter 3 Part 5: 20-day Notice of Right to Claim a Lien, 90-day clerk recording, 5-day post-recording notice, and 2-year lawsuit limitations.
Under MCA § 71-3-531(1), persons who furnish services or materials directly to the owner, wage earners performing labor, and contractors working on commercial properties with 5 or more units are exempt from providing the preliminary 20-day notice.
The claimant must serve a copy of the recorded lien statement on the property owner by personal delivery or certified mail within five (5) business days of filing with the county clerk and recorder. Failure to comply can result in loss of statutory attorney's fees.
Yes. Under MCA § 71-3-562(2), an owner may serve written demand on the lienholder requiring foreclosure action to commence within thirty (30) days. If the claimant fails to file suit within 30 days of receipt, the lien is discharged.