Audit Montana construction lien deadlines under MCA Title 71, Chapter 3, Part 5. Calculate 20-business-day Notice of Right to Claim Lien rules (MCA § 71-3-531), 90-day County Clerk recording deadlines, mandatory 5-day owner notice, and the 2-year district court foreclosure statute of limitations.
Montana Code Annotated (MCA) Title 71, Chapter 3, Part 5 (Construction Liens); MCA § 71-3-531 (Notice of right to claim a lien); § 71-3-535 (Attachment and recording of construction lien); § 71-3-538 (Discharge of lien by bond); § 71-3-562 (Period of limitation for enforcement action).
Under MCA § 71-3-531, a person who provides services or materials to a project and does not have a contract directly with the contracting owner must give a Notice of Right to Claim a Lien to the contracting owner within twenty (20) business days after first furnishing services or materials on residential property (or where a Notice of Commencement is recorded). Late service covers only services or materials provided within the 20 days prior to service and thereafter.
Under MCA § 71-3-535, a claimant must record a Notice of Construction Lien in the office of the county clerk and recorder within ninety (90) calendar days after the claimant's final furnishing of services or materials, or within 90 days after the owner files a Notice of Completion under MCA § 71-3-533.
Under MCA § 71-3-562, a construction lien continues for two (2) years after the date the lien was recorded in the county clerk and recorder's office. The claimant must commence a judicial foreclosure action in the district court within this 2-year period, otherwise the lien automatically terminates and becomes unenforceable.