MCL § 570.1109

Michigan MCL § 570.1109 Notice of Furnishing Auditor

Audit Michigan Construction Lien Act compliance under MCL § 570.1109, 20-day Notice of Furnishing deadlines, Notice of Commencement verification, sworn statements, and 90-day recording timelines.

Case Facts & Contract Parameters

Compliance Verdict & Calculation

Statutory Compliance Verified
Requirements satisfied.

Statutory Checklist

    Statutory Authority & Legal Guidelines

    Frequently Asked Questions

    Who is required to serve a Notice of Furnishing in Michigan?
    Under MCL § 570.1109(1), a subcontractor, supplier, or laborer who provides an improvement to real property and who does not have a direct contractual relationship with the property owner must serve a Notice of Furnishing on the owner's designee and general contractor.
    What is the statutory deadline to serve a Michigan Notice of Furnishing?
    Under MCL § 570.1109, the Notice of Furnishing must be served within 20 days after the date on which the subcontractor or supplier first furnished labor or material to the project site (or within 30 days for laborers).
    What happens if a Notice of Furnishing is served late in Michigan?
    Unlike states with strict retroactive cutoffs, Michigan MCL § 570.1109(6) provides that failure to timely serve the Notice of Furnishing does not defeat a lien, BUT the lien is limited to unpaid amounts. If the owner has paid the general contractor pursuant to a sworn statement (MCL § 570.1110) before receiving the late notice, the lien cannot attach to those previously disbursed funds.
    What is a Notice of Commencement and how does it affect the NOF deadline?
    Under MCL § 570.1108, the owner must record a Notice of Commencement. If the owner fails to record or provide the Notice of Commencement within 10 days of a written request, the claimant's obligation to serve a Notice of Furnishing is tolled until 20 days after the Notice of Commencement is actually provided.
    What is the deadline to record and foreclose a Michigan construction lien?
    Under MCL § 570.1111, a Claim of Lien must be recorded in the county register of deeds within 90 days after the last date of furnishing labor or material. Under MCL § 570.1117, a lawsuit to foreclose the construction lien must be filed within 1 year from the date of recording.