Michigan Construction Lien Act Notice Auditor

MCL § 570.1109 20-Day Notice of Furnishing, Sworn Statement Shield (§ 570.1110), 90-Day Recording, and 1-Year Foreclosure Auditor

Project & Notice Chronology

Lien Validity & Enforceability Assessment

NOTICE TIMELY & PRESERVED
20-Day Notice Deadline
--
90-Day Recording Deadline
--
Enforceable Lien Value
$45,000
Forfeited Pre-Notice Value
$0
Input project milestone dates to calculate Michigan construction lien perfection deadlines.
Statutory Requirement MCL Reference Audit Result
20-Day Notice of FurnishingMCL § 570.1109Pending input
Pre-Notice ForfeitureMCL § 570.1109(5)Pending input
90-Day Claim RecordingMCL § 570.1111Pending input
1-Year Foreclosure SuitMCL § 570.1117Pending input
🏠 Home Hub

Statutory Guidance: Michigan Construction Lien Act

What is the 20-day Notice of Furnishing requirement under MCL § 570.1109?
Under Michigan Compiled Laws § 570.1109, a subcontractor or material supplier who contracts with someone other than the owner must serve a written Notice of Furnishing upon the designee (or owner) and the general contractor within 20 calendar days after first furnishing labor or materials. Service must be made personally or by certified mail with return receipt requested.
What are the legal consequences of serving a late Notice of Furnishing in Michigan?
Under MCL § 570.1109(5), failure to serve the Notice of Furnishing within the 20-day period does NOT completely destroy lien rights, but it forfeits the right to claim a lien for any labor or materials furnished prior to the actual date the Notice of Furnishing is served, to the extent the owner has made payments pursuant to a contractor sworn statement.
What is the deadline for recording and serving a Claim of Lien under MCL § 570.1111?
Under MCL § 570.1111, a Claim of Lien must be recorded in the office of the Register of Deeds in the county where the real property is situated within ninety (90) calendar days after the date the last labor or material was furnished. Within fifteen (15) days after recording, a copy of the recorded claim of lien and proof of service must be served on the owner or designee.
What is the statutory limitation period for filing a foreclosure action in Michigan?
Under MCL § 570.1117, an action to enforce a construction lien through foreclosure must be commenced in the circuit court for the county where the property is located within one (1) year after the date the claim of lien was recorded in the Register of Deeds. Failure to file suit and record a notice of lis pendens within one year completely terminates the lien.