OmniCalc Hub
MASSACHUSETTS CONSTRUCTION LAW • Massachusetts • Mass. Gen. Laws c. 254 § 2, § 4, § 8, § 11

Massachusetts M.G.L. c. 254 Mechanics' Lien Auditor

Calculate strict statutory deadlines under Mass. Gen. Laws ch. 254: audit the three-stage perfection process (Notice of Contract § 2 / § 4, Statement of Account § 8, and Superior Court lawsuit § 11), evaluate Notice of Substantial Completion triggers, and track subcontractor Notice of Identification rules.

All liens in Massachusetts require a written contract on the recording date.
Just amount due for labor performed or materials furnished under written agreement.
Baseline date for calculating 90-day Notice of Contract recording window.
Recording of a Notice of Substantial Completion shortens deadlines to 60 / 90 days.
M.G.L. c. 254 strictly requires written agreement; quantum meruit liens are disallowed.
Step 1 recording date in the County Registry of Deeds.
Step 2 recording date (triggers 90-day enforcement countdown under § 11).

Statutory Legal & Real Estate Analysis: Mass. Gen. Laws c. 254 § 2, § 4, § 8, § 11

What is the three-step statutory process to perfect a mechanics' lien in Massachusetts?
Perfection in Massachusetts requires strict adherence to three successive steps: (1) Record a Notice of Contract in the Registry of Deeds under Section 2 (contractors) or Section 4 (subcontractors); (2) Record a sworn Statement of Account under Section 8 stating the just and true account of the amount due; and (3) File a civil complaint in Superior Court to enforce the lien within 90 days after recording the Statement of Account and record an attested copy of the complaint (lis pendens) in the Registry under Section 5.
How does a recorded Notice of Substantial Completion alter lien deadlines in Massachusetts?
Under M.G.L. c. 254 § 2 and § 4, if a Notice of Substantial Completion is recorded in the Registry of Deeds, the deadline for recording a Notice of Contract is shortened to 60 calendar days from the date of recording that notice. Similarly, the deadline for recording the Statement of Account is shortened to 90 calendar days from that date. If no such notice is recorded, deadlines are measured as 90 days and 120 days from the last date labor or materials were furnished.
Can a contractor or subcontractor file a mechanics' lien without a written contract in Massachusetts?
No. Massachusetts law is unyielding: under M.G.L. c. 254 § 2 and § 4, a mechanics' lien can ONLY be claimed by a person who has entered into a 'written contract.' Oral agreements, quantum meruit claims, or unexecuted purchase orders do not support a mechanics' lien, and Massachusetts courts strictly void any lien not predicated on a binding written agreement.
What is the consequence of missing the 90-day enforcement lawsuit deadline under Section 11?
Under M.G.L. c. 254 § 11, the lien is dissolved automatically as a matter of law unless a civil action to enforce it is commenced in the Superior Court or District Court within 90 calendar days after the filing of the Statement of Account. Furthermore, failure to record an attested copy of the complaint in the Registry of Deeds within 30 days of commencing the action also dissolves the lien.