Calculate mandatory statutory deadlines under Maine Title 10: 90-day Registry of Deeds recording, 120-day judicial enforcement lawsuit cutoffs, and residential owner-occupant double payment safe harbors.
10 M.R.S. § 3253: Clock begins strictly on claimant's last date of substantive work.
Subcontractors without direct owner contract must deliver notice copy to owner.
Lien is strictly capped at the balance owed by owner to prime contractor when notice received.
90 calendar days from last furnishing date.
120 calendar days from last furnishing date (Lien dissolves if missed).
| Statutory Stage | Maine Statute | Deadline / Status |
|---|