Kansas Mechanics' Lien & Warning Statement Auditor

Evaluates Kansas construction lien preservation under K.S.A. 60-1101 through 60-1105, tracking contractor tiers, residential Warning Statements, district court filing deadlines, and lawsuit bars.

1. Contract Tier & Project Data

2. Statutory Lien Audit Results

Lien Rights In Good Standing
Statutory Filing Deadline: 3 Months (~90 Days) from Last Work
Days Remaining to File: 45 Days Remaining
Residential Warning Statement: Satisfied (§ 60-1103a)
Lien Foreclosure Lawsuit Bar: 1 Year from District Court Filing Date
Overall Enforceability: Preserved
Lien statement is in good standing under K.S.A. 60-1103. Subcontractor has approximately 45 days remaining to file the verified lien statement with the Clerk of the District Court.

3. Kansas Mechanics' Lien Statutory Framework (K.S.A. Chapter 60 Article 11)

Claimant Category Governing Section Filing Deadline Special Notice Requirements
General Contractor K.S.A. 60-1102 4 months from last labor/materials Can extend to 5 months via Notice of Intent to Perform.
Subcontractor / Supplier K.S.A. 60-1103 3 months from last labor/materials Certified mail service on owner within 30 days of filing.
Residential Subcontractor K.S.A. 60-1103a 3 months from last labor/materials Mandatory pre-payment Warning Statement to owner.
Foreclosure Lawsuit (All) K.S.A. 60-1105 1 year from filing date Action in District Court + Lis Pendens recording.

Frequently Asked Questions on Kansas Mechanics' Liens

What are the filing deadlines for mechanics' liens in Kansas?

Under Kansas law: (1) General contractors (direct contract with owner) must file their lien statement with the Clerk of the District Court within 4 months after the date material, equipment, or labor was last supplied (K.S.A. 60-1102); (2) Subcontractors and suppliers must file within 3 months after last supplying labor or materials (K.S.A. 60-1103).

Can the general contractor extend the 4-month filing deadline in Kansas?

Yes. Under K.S.A. 60-1102, a contractor may extend the filing deadline from 4 months to 5 months by filing a Notice of Intent to Perform with the Clerk of the District Court prior to the expiration of the initial 4-month period.

What is the mandatory Warning Statement for residential construction in Kansas?

Under K.S.A. 60-1103a, subcontractors furnishing labor or materials for existing residential property must deliver a statutory 'Warning Statement' to the property owner. If the owner pays the general contractor before receiving this statement, the subcontractor's lien rights are extinguished to the extent of such payment.

How long does a claimant have to initiate a lien foreclosure lawsuit in Kansas?

Under K.S.A. 60-1105, an action to foreclose a mechanics' lien must be commenced in District Court within 1 year from the date the lien statement was filed with the Clerk of the District Court. Missing this 1-year deadline automatically extinguishes the lien.