Illinois 770 ILCS 60 Mechanics Lien Statutory Guidance
What is the 90-day notice requirement under 770 ILCS 60/24?
Under Section 24(a) of the Illinois Mechanics Lien Act (770 ILCS 60/24(a)), a subcontractor must send written notice of its claim and the amount due or to become due to the property owner, or the owner's agent or architect, and to any lending institution holding an encumbrance/mortgage, within 90 calendar days after completion of the subcontractor's work.
What is the Section 5 Sworn Statement exception to the 90-day notice?
Under Illinois Supreme Court precedent (Weather-Tite, Inc. v. University of St. Francis, 233 Ill. 2d 385), a subcontractor is not required to serve a Section 24 90-day notice if the general contractor has listed the subcontractor and the correct amount owed to that subcontractor in a sworn contractor's statement under 770 ILCS 60/5 provided to the owner.
What is the 4-month recording deadline under 770 ILCS 60/7?
Under 770 ILCS 60/7, to enforce a mechanics lien against third parties (such as mortgage lenders, encumbrancers, or subsequent purchasers), the contractor or subcontractor must file a claim for lien in the office of the recorder of deeds in the county where the property is situated within 4 months after the completion of work.
What special notice is required for single-family owner-occupied homes?
Under 770 ILCS 60/5(b), in the case of single-family owner-occupied residences, each subcontractor must provide a 60-day notice to the owner within 60 calendar days of first furnishing labor or materials. Failure to provide this 60-day preliminary notice limits the subcontractor's lien to unpaid funds remaining in the owner's hands.
What is the statute of limitations to file an enforcement suit in Illinois?
Under 770 ILCS 60/9, a lawsuit to foreclose an Illinois mechanics lien must be commenced within 2 years after the completion of work. Additionally, under Section 34, an owner may serve a demand letter requiring the lienholder to file suit within 30 days, or forfeit the lien.