Illinois Mechanics Lien Act (770 ILCS 60) Deadline Auditor

Complete statutory calculator and procedural compliance auditor for Illinois mechanics' liens. Audits subcontractor 90-day notices (§ 24), owner-occupied residential 60-day notices (§ 5/21), 4-month recording deadlines against third parties (§ 7), Section 34 30-day demand suits, and 2-year lawsuit expirations.

Project & Work Timeline

Clock runs strictly from completion; repair/warranty work does not extend (§ 7).

Statutory Deadlines & Priority Status

LIEN RIGHTS ACTIVE & TIMELY
90-Day Notice Cutoff
--
4-Month Recording Limit
--
Days to Record Claim
--
2-Year Lawsuit Expiry
--

Illinois Mechanics Lien Act (770 ILCS 60) Precedents

What is the 90-day subcontractor notice requirement under 770 ILCS 60/24?
Under 770 ILCS 60/24(a), a subcontractor must send written notice of its claim to the property owner (and any lending agency) within 90 calendar days after the date of completion of its work or final delivery of materials. Notice must be served via certified mail, return receipt requested, or personal delivery.
Why is the 4-month recording deadline under Section 7 critical in Illinois?
Under 770 ILCS 60/7, to enforce a mechanics' lien against third parties (such as subsequent purchasers, mortgage lenders, or other encumbrancers), the lien claim must be recorded with the County Recorder of Deeds within 4 months after completion of the work. If recorded after 4 months but within 2 years, the lien is enforceable only against the original owner.
What happens if an owner serves a Section 34 Demand to commence suit?
Under 770 ILCS 60/34, an owner or interested party may serve a formal written demand requiring the lien claimant to file a lawsuit to enforce the lien within 30 calendar days. If the claimant fails to commence suit within 30 days of receiving the demand, the mechanics' lien is forfeited and completely extinguished.
What special 60-day notice applies to owner-occupied residential properties?
Under 770 ILCS 60/5 and 60/21(c), for owner-occupied single-family residential projects, a subcontractor must provide a statutory Notice of Furnishing to the occupant-owner within 60 calendar days of first providing labor or materials. Failure to provide this 60-day notice limits the subcontractor's lien to the unpaid balance owed by the owner to the contractor at the time notice is actually received.
How does the Illinois Mechanics Lien Act treat sworn contractor statements under Section 5?
Under 770 ILCS 60/5, before the owner pays any money to the contractor, the owner must require, and the contractor must give, a sworn statement in writing listing all subcontractors, trades, amounts due or to become due. If the owner makes payments to the prime contractor without obtaining this sworn statement, such payments are made at the owner's peril and do not defeat subcontractor lien rights under Section 21.
Can a mechanics' lien claimant recover attorney fees in Illinois?
Under 770 ILCS 60/17(b), if the court determines that the property owner failed to pay the lien claim without just cause or right, the court may award reasonable attorney fees to the prevailing lien claimant. Conversely, under subsection (c), if a claimant brings a claim without just cause or right, the owner may recover attorney fees.