Georgia Mechanics' Lien Auditor

O.C.G.A. § 44-14-361 Notice to Contractor, 90-Day Filing & 365-Day Lawsuit Modeler

Determines whether Notice to Contractor applies.
Unpaid amount for labor, materials, or services.
Notice to Contractor deadline: 30 days (§ 44-14-361.5).
Recording deadline: strictly within 90 calendar days.
Enforcement suit deadline: within 365 calendar days.

Statutory Architecture & Legal Explanations

What is the Notice to Contractor requirement under O.C.G.A. § 44-14-361.5?
If the owner or contractor files a Notice of Commencement in the superior court within 15 days of starting work and posts it at the jobsite, any remote subcontractor or materialman who does not have direct privity of contract with the prime contractor must serve a formal statutory Notice to Contractor within 30 days from the first day of furnishing labor, services, or materials. Failure to serve this notice bars all mechanics' lien rights.
What is the recording deadline for a claim of lien in Georgia?
Under O.C.G.A. § 44-14-361.1(a)(2), a claim of lien must be filed for record in the office of the clerk of the superior court of the county where the property is located within 90 days after the completion of the work or the last day on which labor, services, or materials were furnished. This 90-day deadline is strictly enforced; a lien filed on day 91 is void.
How and when must a copy of the recorded lien be served on the owner?
Under O.C.G.A. § 44-14-361.1(a)(2), the lien claimant must send a copy of the claim of lien to the property owner or contractor by registered mail, certified mail, or statutory overnight delivery no later than 3 business days after filing the lien for record.
What is the deadline to commence an enforcement lawsuit in Georgia?
Under O.C.G.A. § 44-14-361.1(a)(3), the lien claimant must commence an action for the recovery of the amount of the lien claim within 365 days from the date of filing the lien for record. Additionally, within 30 days after commencing the action, the claimant must file a Notice of Filing of Action with the clerk of the superior court to maintain the lien against third parties.
What happens if an owner files a Notice of Contest of Lien under § 44-14-368?
An owner or contractor may file a Notice of Contest of Lien under O.C.G.A. § 44-14-368. Once served on the lien claimant, the claimant's deadline to commence an action to enforce the lien is accelerated from 365 days down to 60 days from the receipt of the notice of contest.
Can lien rights be waived in advance of payment in Georgia?
Under O.C.G.A. § 44-14-366, any agreement to waive lien rights in advance of furnishing labor or materials is void and against public policy. Georgia strictly requires statutory interim and final lien waivers. Following 2021 statutory revisions, an executed waiver becomes ineffective if the claimant files an Affidavit of Nonpayment within 60 days of executing the waiver.