What is the 45-day Notice to Owner (NTO) requirement under Fla. Stat. § 713.06(2)(a)?
Under Fla. Stat. § 713.06(2)(a), all lienors not in direct privity of contract with the owner (subcontractors, sub-subcontractors, materialmen) must serve a written Notice to Owner (NTO) no later than 45 calendar days after commencing to furnish labor, services, or materials, and before the date of the owner's final payment to the direct contractor. Florida courts strictly enforce this deadline (strictissimi juris); serving on day 46 completely destroys the lien.
What is the deadline to record a Claim of Lien under Fla. Stat. § 713.08(5)?
The Claim of Lien must be recorded in the public records of the county where the real property is located no later than 90 calendar days after the final furnishing of labor, services, or materials by the lienor. Warranty work or punch-list repairs cannot extend this 90-day period.
How and when must a copy of the Claim of Lien be served on the owner?
Under Fla. Stat. § 713.08(4)(c), the lienor must serve a copy of the claim of lien on the owner before recording or within 15 calendar days after recording. Failure to serve the copy within 15 days renders the lien voidable to the extent the owner was prejudiced by the delay.
What is the statute of limitations to enforce a Florida construction lien?
Under Fla. Stat. § 713.22(1), an action to foreclose a construction lien must be commenced within 1 year from the date the claim of lien was recorded. If no action is filed within 1 year, the lien expires automatically.
How does a Notice of Contest of Lien shorten the lawsuit period under § 713.22(2)?
An owner or contractor can file a formal Notice of Contest of Lien in the county clerk's office under Fla. Stat. § 713.22(2). Once the clerk mails the notice to the lienor, the lienor's deadline to file a foreclosure lawsuit is accelerated from 1 year to just 60 calendar days from the date of mailing. Failure to file suit within 60 days extinguishes the lien.
What is the Contractor's Final Payment Affidavit under § 713.06(3)(d)?
A direct (prime) contractor must deliver a Contractor's Final Payment Affidavit to the owner at least 5 days before filing a lawsuit to enforce a lien. The affidavit must list all lienors under the direct contractor who have not been paid in full. Failure to furnish this affidavit is a fatal jurisdictional defect barring the lawsuit.