Connecticut C.G.S. § 49-34 Mechanics' Lien Auditor

Calculate statutory mechanics' lien deadlines under Connecticut General Statutes § 49-34: track the strict 90-day Town Clerk certificate recording deadline, audit state marshal service on the owner (§ 49-34(2)), verify subcontractor contract price ceilings (§ 49-36), and calculate the 1-year foreclosure limitation (§ 49-39).

C.G.S. § 49-34(1) strict 90-day recording window runs from this date.
Amount justly due for labor performed or materials furnished.
Subcontractors not having direct contract with owner require formal Notice of Intent (§ 49-35).
Under C.G.S. § 49-36, subcontractor liens cannot exceed the unpaid prime contract balance.
Date filed in the Town Clerk's land records of the town where the building is situated.
Copy must be served within 90 days of work cessation or 30 days of recording.
Connecticut courts strictly void liens lacking a proper sworn oath (J.C. Penney Properties).
C.G.S. § 49-39 requires recording a notice of lis pendens to preserve foreclosure action.

Statutory Legal & Regulatory Analysis: Conn. Gen. Stat. § 49-34, § 49-35, § 49-36, § 49-39

What is the recording deadline for a mechanics' lien under Connecticut C.G.S. § 49-34?
Under Conn. Gen. Stat. § 49-34(1), a certificate of mechanics' lien must be lodged with the town clerk of the town in which the building, lot, or plot of land is situated within strict 90 calendar days after the claimant ceased performing services or furnishing materials. This 90-day deadline is strictly jurisdictional and cannot be extended by agreement.
What are the service requirements for a mechanics' lien certificate in Connecticut?
Under C.G.S. § 49-34(2), a true and attested copy of the certificate must be served upon the owner or one of the owners of the property within the same 90-day period or within 30 days after lodging the certificate with the town clerk. Service must be made by a state marshal or other proper officer personally or at the owner's usual place of abode, or by registered/certified mail if the owner is not a resident of the town.
Why is the 'sworn to' requirement so strictly enforced in Connecticut?
C.G.S. § 49-34 requires that the certificate be 'subscribed and sworn to' by the claimant. The Connecticut Supreme Court (in landmark cases like J.C. Penney Properties, Inc. v. Peter M. Santella Co.) has held that a simple acknowledgment is insufficient; the certificate must contain a formal oath administered by a notary or magistrate swearing to the truth of the facts stated. An unsworn certificate renders the lien completely void.
How does C.G.S. § 49-36 limit subcontractor recovery against an owner?
Under C.G.S. § 49-36, no mechanics' lien can attach in favor of any subcontractor or supplier to a greater amount in the whole than the amount which the owner agreed to pay to the general contractor under the prime contract, minus payments made in good faith before receiving notice of lien. Connecticut operates as a strict 'unpaid balance' state.