Audit Colorado mechanics' lien timing under C.R.S. § 38-22-109, model the mandatory 10-day Notice of Intent (NOI) service rule, 4-month recording deadline, and 6-month foreclosure lawsuit bar.
| 10-Day Statutory NOI Waiting Period | Satisfied (12 Days ≥ 10 Days) |
|---|---|
| Earliest Permitted Recording Date | -- |
| Strict 4-Month Recording Deadline | -- |
| Days Remaining to Record Lien | -- |
| 6-Month Foreclosure Lawsuit Deadline | -- |
| Enforceable Mechanics' Lien Principal | $65,000 |
Colorado provides extraordinary protection for construction trade professionals, granting mechanic liens priority over unrecorded deeds of trust and construction mortgages:
Unlike many states where liens are filed without warning, Colorado gives owners a 10-day settlement window. A lien recorded on day 9 after NOI is legally void and uncorrectable after the 4-month window closes.
Punch list items, warranty work, and trivial repairs do NOT extend the 4-month clock under settled Colorado case law (Storke Associates). Only substantial, authorized contract work resets the last work date.
All funds disbursed to any contractor or subcontractor for construction work constitute trust funds. Diverting construction draws to other projects or general overhead triggers civil theft treble damages and attorney fees.
Recording a mechanics' lien without statutory compliance or for an inflated dispute is subject to Colorado's Spurious Lien Act, exposing the claimant to mandatory statutory fines of $1,000+ and owner attorney's fees.