California Construction Law • Civil Code §§ 8814 & 8818

California Civil Code § 8814 Retention Prompt Payment Auditor

Audit private works retention payment deadlines under California Civil Code § 8814. Calculate 10-day contractor disbursement requirements, maximum 150% bona fide dispute withholding caps, and 2% per month statutory penalty liability under § 8818.

📋 Retention & Timing Parameters

Total retainage owed to the trade subcontractor.
Triggers 10-day statutory disbursement deadline under § 8814(a).
Under § 8814(c), contractor may withhold max 150% of this amount.
Used to calculate months of delay and 2%/month statutory penalties.

⚖️ Statutory Findings & 2%/Mo Penalties

Input parameters and click "Audit Prompt Payment Penalties"
10-Day Statutory Due Date
--
Improperly Withheld
$0
2%/Mo Penalty Accrued
$0
Total Contractor Liability
$75,000

Statutory Verification Breakdown:

Awaiting parameters to audit California Civil Code § 8814.

Statutory Architecture of California Civil Code § 8814 & § 8818

Under California private works construction law, retainage withholding is governed by strict statutory prompt payment mandates designed to protect downstream trade subcontractors from cash flow abuse by general contractors and developers.

Under California Civil Code § 8814(a), within 10 calendar days after receipt of retention proceeds by the direct contractor or higher-tier subcontractor, the contractor must disburse to each subcontractor their respective share of the retention withheld. If an owner withholds retention beyond 45 days after completion (§ 8812), or if a contractor fails to disburse within 10 days, severe statutory consequences follow.

The only statutory exception is set forth in Civil Code § 8814(c): if a bona fide dispute exists between the contractor and subcontractor, the contractor may withhold an amount not exceeding 150 percent of the estimated value of the disputed work. Any retention withheld in excess of 150% is statutorily wrongful.

Under Civil Code § 8818, an entity that wrongfully withholds retention beyond statutory deadlines is subject to a non-waivable statutory penalty of 2 percent per month on the improperly withheld balance, in lieu of interest, plus mandatory attorney's fees to the prevailing subcontractor.

Frequently Asked Questions Regarding California Civil Code § 8814

What is the prompt payment deadline for retention under California Civil Code § 8814?
Under California Civil Code § 8814(a), within 10 calendar days after receipt of retention proceeds by the direct contractor or higher-tier subcontractor, the contractor must pay to each subcontractor their respective share of the retention withheld.
How much retention can a contractor withhold if there is a bona fide dispute?
Under California Civil Code § 8814(c), if a bona fide dispute exists between a contractor and a subcontractor, the contractor may withhold from the retention payment an amount not to exceed 150 percent of the estimated value of the disputed amount.
What are the penalties for wrongfully withholding retention under California law?
Under California Civil Code § 8818, if retention is not paid within the statutory deadlines and is wrongfully withheld, the person withholding the payment is subject to a mandatory penalty of 2 percent per month on the improperly withheld balance, in lieu of interest, plus reasonable attorney's fees to the prevailing party.
Can parties contractually waive the 10-day retention payment requirement or 2% penalty?
No. California prompt payment statutes represent strong public policy. Any contract provision attempting to waive, modify, or condition the statutory prompt payment deadlines or 2% monthly penalties is void and unenforceable as against public policy.
When must the owner release retention to the direct contractor under California law?
Under California Civil Code § 8812, an owner must release retention proceeds to the direct contractor within 45 days after the date of completion of the work of improvement.