Audit owner 30-day progress payments, general contractor 7-day subcontractor distributions, 150% bona fide dispute retention limits, and 2% monthly statutory interest penalties.
Directly related to current work (*United Riggers*). Max legal withholding: 150% ($30,000).
Under California appellate interpretations, the 2% per month penalty is calculated on a per-diem basis (2% / 30 = 0.0667% per day) on the amount wrongfully withheld for each day beyond the statutory deadline until the payment is cured or resolved in arbitration/court.
In United Riggers & Erectors, Inc. v. Coast Iron & Steel Co., 4 Cal. 5th 1082 (2018), the court ruled that the 150% dispute exception only applies to disputes directly concerning the specific work or payment being billed. A contractor cannot withhold progress payments on Project A because of a dispute on Project B, nor withhold progress money due to a dispute over unrelated delay damages.
The 7-calendar-day clock starts on the date the direct contractor actually receives progress funds from the owner. If the direct contractor fails to pay the subcontractor within 7 days, the subcontractor is immediately entitled to the 2% monthly penalty on its unpaid share, regardless of any pay-if-paid clauses.
Under the landmark decision in Wm. R. Clarke Corp. v. Safeco Ins. Co., 15 Cal. 4th 882 (1997), 'pay-if-paid' clauses that make owner payment an absolute condition precedent to paying subcontractors are void and unenforceable as against public policy in California because they interfere with constitutionally protected mechanic's lien and prompt pay rights.
Retention payments are subject to a separate statutory timeline: an owner must release retention within 45 days after completion of the work of improvement, and a direct contractor must disburse each subcontractor's share of retention within 10 days of receiving retention funds.