Determine statutory construction lien deadlines under Alaska Statutes Title 34 Chapter 35, verify Notice of Right to Lien (§ 34.35.064), calculate 120-day vs. 15-day recording rules, and track 6-month foreclosure limits.

Project & Work Timeline

Statutory Deadlines & Enforcement Status

Alaska Mechanics Lien Validity Status
TIMELY RECORDED & ENFORCEABLE

Lien recorded within statutory window under AS § 34.35.068.

Dec 30, 2026
Recording Deadline
May 15, 2027
6-Mo Foreclosure Deadline
Eligible (R. 82)
Prevailing Fees

Statutory Milestone Audit

Statutory Milestone Statutory Rule Calculated Date / Status
Calculating milestones...
Alaska Statutes Reference: AS §§ 34.35.050 - 34.35.120. Under AS 34.35.110, an action to enforce the lien must be commenced in superior court within 6 months after recording, or the lien expires by operation of law.
🏠 Home Hub

Frequently Asked Statutory Questions (FAQ)

What is the Alaska Notice of Right to Lien under AS § 34.35.064? ▼
Under AS § 34.35.064, a potential lien claimant (subcontractor or supplier not under direct contract with the owner) may give a Notice of Right to Lien to the property owner. If an owner records a Notice of Completion, only claimants who gave a timely Notice of Right to Lien (or who have already recorded a claim of lien) are entitled to receive personal notice of the completion and maintain lien rights.
What is the statutory deadline for recording a claim of lien in Alaska? ▼
Under AS § 34.35.068, a claim of lien must be recorded in the recording district where the property is located within 120 days after the claimant stops furnishing labor, services, materials, or equipment, OR within 15 days after the owner records a valid Notice of Completion and gives required statutory notice to eligible claimants.
What is the statute of limitations for filing a foreclosure action on an Alaska mechanics lien? ▼
Under AS § 34.35.110, an action to enforce an Alaska mechanics lien must be commenced in superior court within six (6) months after the lien is recorded. If an action is not filed within 6 months, the lien automatically expires and becomes void.
Can a lien claimant recover attorney fees in an Alaska lien foreclosure action? ▼
Yes. Under AS § 34.35.005(b) and Civil Rule 82, in an action to enforce a lien under AS 34.35, the prevailing party is entitled to recover reasonable attorney fees and costs incurred in the action and in preparing and recording the lien claim.