Statutory Framework: Alabama Mechanics' and Materialmen's Liens
Alabama's mechanics' lien statutes (Ala. Code § 35-11-210 through § 35-11-234) are strictly construed by Alabama courts. Failure to adhere precisely to statutory notice protocols, recording windows, and lawsuit deadlines results in total forfeiture of lien rights.
The Critical Distinction: Full Price vs Unpaid Balance Liens
Alabama is one of the few jurisdictions establishing a bifurcated lien scheme for subcontractors and materialmen:
- Full Price Lien: Secures the entire dollar value of the materials or labor furnished, even if the property owner has already paid the general contractor in full. To obtain this super-priority protection, the supplier or sub must deliver written notice to the owner BEFORE furnishing any materials. If the owner does not provide written notice of non-responsibility before delivery, the full price lien attaches.
- Unpaid Balance Lien: If notice is given after materials have already been furnished, the lien attaches only to the unpaid balance remaining due from the owner to the general contractor at the exact time the owner receives written notice of the lien claim. If the owner has paid the GC in full, an unpaid balance lien secures $0.
Filing Deadlines in Alabama Probate Court (§ 35-11-215)
Every claimant must file a verified statement of lien in the Office of the Judge of Probate in the county where the property is located. Deadlines are measured from the last item of work or materials furnished:
- Original Contractors (Direct with Owner): 6 months.
- Subcontractors, Materialmen, and Suppliers: 4 months.
- Day Laborers: 30 days.
Lawsuit Statute of Limitations (§ 35-11-221)
Under Alabama Code § 35-11-221, an action to enforce a mechanics' lien must be commenced in Circuit Court within 6 months after the maturity of the entire indebtedness. Maturity occurs when payment becomes due under the terms of the contract or invoice. Filing suit after this 6-month window renders the lien void as a matter of law.
Frequently Asked Questions: Alabama Construction Liens
What is the difference between a 'Full Price Lien' and an 'Unpaid Balance Lien' in Alabama?
Under Ala. Code § 35-11-210, a materialman or subcontractor obtains a 'Full Price Lien' (securing the full value of materials furnished) ONLY IF they deliver written notice to the property owner BEFORE furnishing materials, and the owner does not object in writing prior to delivery. If notice is given AFTER materials are furnished, the claimant obtains only an 'Unpaid Balance Lien', which attaches solely to the unpaid contract funds remaining due from the owner to the general contractor at the time notice is received.
What is the deadline for filing a verified statement of lien in the Alabama Probate Court?
Under Ala. Code § 35-11-215, the verified statement of lien must be filed in the Office of the Judge of Probate in the county where the property is situated within: (1) 6 months after the last item of work or materials for original/general contractors, (2) 4 months for subcontractors and materialmen, or (3) 30 days for day laborers.
What is the statute of limitations to file an Alabama mechanics' lien foreclosure lawsuit?
Under Ala. Code § 35-11-221, any action for the enforcement of a mechanics' lien must be commenced in the Circuit Court within 6 months after the maturity of the entire indebtedness secured thereby.
Does an Alabama mechanics' lien extend to the land or only the building improvement?
Under Ala. Code § 35-11-210, the lien attaches to the building or improvement and the land on which the same is situated, to the extent of all the right, title, and interest owned by the owner or proprietor (including up to one acre outside a city, or the entire lot within a city).