EPA NPDES CGP & SWPPP Stormwater Auditor
Determine stormwater inspection intervals, storm runoff thresholds, and stabilization deadlines under 40 CFR 122.26.
SWPPP Inspection & Stabilization Schedule
Mandatory Inspection Interval
24-Hour Rain Trigger Status
Stabilization Completion Deadline
| Sediment Cleanout Requirement: | |
| Corrective Action Documentation Deadline: | Within 24 hours of finding; Complete repairs ≤ 7 calendar days |
| EPA Clean Water Act Statutory Fines: | Up to $64,618 per day per violation under adjusted federal civil monetary penalties |
EPA 2022 CGP Rules
- Sensitive Receiving Waters: If discharging to Tier 2/3 or impaired water, inspections are required once every 7 calendar days AND within 24h of 0.25" rain.
- 5-Acre Threshold: Sites disturbing > 5 acres must finish stabilization within 7 days; smaller sites within 14 days.
- Rain Gauge: Operators must maintain an on-site rain gauge or reference daily local NOAA weather station records.