Wisconsin Construction Lien Auditor

Determine 60-day subcontractor identification notices, mandatory 30-day notice of intent, and 6-month circuit court filing limits.

Wisconsin Chapter 779 Statutory Findings

60-Day Identification Notice
6-Month Claim for Lien Due
Latest 30-Day Notice of Intent
Two-Step Subcontractor Rule:Must serve 60-day preliminary notice AND 30-day notice of intent prior to filing
Foreclosure Lawsuit Filing Window:Action must be commenced within 2 years from filing Claim for Lien (Wis. Stat. § 779.06(1))
Lien Priority Status:Relates back to the date of visible commencement of work on the improvement
Wis. Stat. § 779 Rules
  • 60-Day Identification: Subcontractors on residential projects must serve notice within 60 days of first work. Commercial projects with >4 family units are exempt.
  • 30-Day Mandatory Intent: A Claim for Lien cannot be recorded until at least 30 days after serving a Notice of Intent to File.
  • 6-Month Circuit Court Cap: Counted strictly from the last date of furnishing labor or materials.