Under SDCL § 44-9-15, the lien statement must be filed with the register of deeds of the county where the property is located within one hundred twenty (120) days after the claimant's last date of furnishing labor or materials.
Under SDCL § 44-9-15, a copy of the lien statement must be mailed to the owner at their last known address by registered or certified mail, and the post office receipt must be attached to the statement filed with the register of deeds.
Under SDCL § 44-9-24, an action to enforce a mechanics lien must be commenced within six (6) years after the date of the last item in the claim, unless the owner serves a 30-day demand to commence action under SDCL § 44-9-26.