South Dakota SDCL Chapter 44-9 Mechanics' Lien Auditor

Audit South Dakota mechanics lien deadlines under SDCL § 44-9-15: 120-day county register of deeds recording, post-filing notice, and 6-year court lawsuit limitation.
South Dakota Codified Laws (SDCL) Chapter 44-9 (Mechanics' and Materialmen's Liens)

Statutory Parameters

Statutory Compliance FAQ (People Also Ask)

What is the deadline to file a mechanics lien in South Dakota?

Under SDCL § 44-9-15, the lien statement must be filed with the register of deeds of the county where the property is located within one hundred twenty (120) days after the claimant's last date of furnishing labor or materials.

What service on the property owner is required under South Dakota law?

Under SDCL § 44-9-15, a copy of the lien statement must be mailed to the owner at their last known address by registered or certified mail, and the post office receipt must be attached to the statement filed with the register of deeds.

How long is a South Dakota mechanics lien enforceable?

Under SDCL § 44-9-24, an action to enforce a mechanics lien must be commenced within six (6) years after the date of the last item in the claim, unless the owner serves a 30-day demand to commence action under SDCL § 44-9-26.