S.C. Code Ann. Title 29, Chapter 5

South Carolina Mechanics Lien Auditor

Audit South Carolina mechanics lien deadlines: 90-day Register of Deeds recording and 6-month foreclosure filing requirements under S.C. Code § 29-5-90 and § 29-5-120.

Claim Dates & Characteristics
$
If a Notice of Project Commencement is filed, remote sub-subcontractors must serve a Notice of Furnishing under § 29-5-20 to preserve lien rights.
Title 29 Compliance Result
Click "Audit South Carolina Statutory Deadlines" to calculate filing deadlines.