Under 42 O.S. § 142.6, subcontractors and suppliers on commercial properties or multi-unit residential properties (more than 4 units) must send a statutory pre-lien notice to the property owner and general contractor within 75 days of last performing work or supplying materials.
Under 42 O.S. § 142, an original/prime contractor must file a lien statement with the county clerk within 4 months after the date labor or materials were last furnished. Under 42 O.S. § 143, a subcontractor or supplier must file within 90 days after the last furnishing.
Under 42 O.S. § 172, an action to enforce a mechanics lien must be commenced in district court within 1 year from the date the lien statement was filed with the county clerk.