Under NDCC § 35-27-05, a claimant must serve written notice of intent to claim a lien on the property owner by registered or certified mail at least fifteen (15) days before recording the lien statement with the county recorder.
Under NDCC § 35-27-13, a construction lien must be recorded within ninety (90) days after the final contribution of labor, skill, or materials. Recording after 90 days preserves the lien against the owner but subordinates it to intervening bona fide purchasers.
Under NDCC § 35-27-24, a construction lien remains enforceable for three (3) years after recording. However, under § 35-27-25, if the property owner serves a written demand to sue, the claimant must commence suit within thirty (30) days.