North Carolina Lien Agent & Chapter 44A Auditor

Determine LiensNC appointment triggers, 15-day Notice to Lien Agent deadlines, 120-day filing limits, and 180-day lawsuit requirements.

NC Chapter 44A Statutory Findings & Deadlines

Lien Agent Mandate
120-Day Claim of Lien Deadline
180-Day Lawsuit Deadline
15-Day Notice to Lien Agent (NLA):
Recording Venue:Clerk of Superior Court in the county where real property is situated
Service on Property Owner:Mandatory copy of Claim of Lien must be served on owner contemporaneously with filing
Subcontractor Subrogation Rights:Right to Claim of Lien on Real Property by subrogation under N.C.G.S. § 44A-23
N.C.G.S. § 44A Essentials
  • $30,000 Threshold: Projects ≥ $30,000 mandate LiensNC registration before building permits are issued.
  • Notice to Lien Agent: Must be given within 15 days of first furnishing to preserve priority against subsequent purchasers or lenders.
  • 120 & 180 Days: Strict counting from the last date of furnishing (120 days to record claim, 180 days to file lawsuit).