Under NRS 108.226, a claimant must record a notice of lien within 90 days after the completion of the work of improvement or last furnishing of labor/materials, OR within 40 days after the owner records and serves a statutory Notice of Completion, whichever is earlier.
Under NRS 108.245, any subcontractor, supplier, or equipment lessor who does not have a direct contract with the property owner must deliver a Notice of Right to Lien to the owner within 31 days after first furnishing labor, materials, or equipment.
Under NRS 108.233, an action to foreclose a mechanics lien must be commenced in court within 6 months after the notice of lien is recorded in the county recorder's office; otherwise, the lien expires and becomes void.