Under Neb. Rev. Stat. § 52-137, a claimant must record a construction lien with the register of deeds no later than 120 days after the final date on which services or materials were furnished.
Yes. Under Neb. Rev. Stat. § 52-135(3), the claimant must send a copy of the recorded lien to the contracting owner within 10 days after recording. Failure to send the notice within 10 days leaves the lien unenforceable until notice is actually served.
Under Neb. Rev. Stat. § 52-140, a construction lien remains enforceable for two years after recording, unless the owner demands that the claimant initiate judicial proceedings within 30 days.