Montana Construction Lien Act Title 71 Statutory Auditor

Audit Montana MCA § 71-3-531 preliminary notice of right to claim lien (20 days), 90-day county recording deadlines, and 2-year lawsuit enforcement windows.
Montana Code Annotated (MCA) Title 71 Chapter 3 Part 5 (Construction Lien Act)

Statutory Parameters

Statutory Compliance FAQ (People Also Ask)

Who must serve a preliminary notice under the Montana Construction Lien Act?

Under MCA § 71-3-531, any subcontractor, material supplier, or laborer who does not have a direct contract with the property owner must serve a Notice of Right to Claim a Lien within twenty (20) days of first providing services or materials.

What is the deadline to record a mechanics lien in Montana?

Under MCA § 71-3-535, a person claiming a construction lien must record the lien with the county clerk and recorder within ninety (90) days after final completion or the last date services or materials were furnished.

How long is a construction lien enforceable in Montana courts?

Under MCA § 71-3-562, an action to enforce a construction lien must be commenced in district court within two (2) years after the date the lien was recorded with the county clerk, or the lien is automatically extinguished.