Under MCA § 71-3-531, any subcontractor, material supplier, or laborer who does not have a direct contract with the property owner must serve a Notice of Right to Claim a Lien within twenty (20) days of first providing services or materials.
Under MCA § 71-3-535, a person claiming a construction lien must record the lien with the county clerk and recorder within ninety (90) days after final completion or the last date services or materials were furnished.
Under MCA § 71-3-562, an action to enforce a construction lien must be commenced in district court within two (2) years after the date the lien was recorded with the county clerk, or the lien is automatically extinguished.